Bluestem
A 198 MW wind power plant in Beaver, Oklahoma, owned by Bluestem Wind Energy, LLC, commissioned in 2016.
Facility nameplate · EIA Plant ID 60256Wind
Nameplate capacity
198 MW
Primary fuel
Wind
Commissioned
2016
Time in queue (2011→2016)
5.7 yrs
Owner
Bluestem Wind Energy, LLC
Location
Beaver, Oklahoma
Coordinates
Generation (2024)
814.8 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1
This facility was matched to a SPP interconnection request (LBNL Queued Up): queued 2011, commercial operation 2016 — 5.7 years in the queue. See the SPP queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2016 | 13.5 | |
| 2017 | 794.2 | |
| 2018 | 837.8 | |
| 2019 | 814.2 | |
| 2020 | 811.9 | |
| 2021 | 809.6 | |
| 2022 | 812.2 | |
| 2023 | 750.3 | |
| 2024 | 814.8 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Ponderosa Wind Energy Center | Wind | 200 MW | ~7 km |
| Ponderosa Wind II | Wind | 100 MW | ~20 km |
| Balko Wind LLC | Wind | 299.7 MW | ~23 km |
| Palo Duro Wind | Wind | 249.9 MW | ~50 km |
| Tri County - TenK | Solar | 1 MW | ~64 km |
| Laverne Diesel Generating Plant | Oil | 4 MW | ~65 km |
See all wind plants in Oklahoma or browse all plants in Oklahoma.