Chestnut Flats Wind Farm

A 38 MW wind power plant in Blair, Pennsylvania, owned by EDF Renewable Asset Holdings, Inc., commissioned in 2011.

Facility nameplate · EIA Plant ID 57268Wind
Nameplate capacity
38 MW
Primary fuel
Wind
Commissioned
2011
Time in queue (20062011)
4.9 yrs
Owner
EDF Renewable Asset Holdings, Inc.
Location
Generation (2024)
90.7 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1

This facility was matched to a PJM Interconnection interconnection request (LBNL Queued Up): queued 2006, commercial operation 2011 4.9 years in the queue. See the PJM queue or typical durations.

Reported annual generation

YearGWh
2015102.1
2016106.3
2017103.2
201887.4
201986.3
202099
202188.2
202294.1
202392.8
202490.7

Nearby power plants

PlantFuelCapacityDistance
Juniata Locomotive ShopNatural Gas1.5 MW~8 km
North Allegheny Windpower ProjectWind75 MW~11 km
Allegheny Ridge Wind FarmWind80 MW~18 km
Patton Wind FarmWind30 MW~22 km
CPV Maple Hill SolarSolar100 MW~24 km
Ebensburg PowerCoal57.6 MW~24 km