Chestnut Ridge Gas Recovery

A 4.8 MW waste power plant in Anderson, Tennessee, owned by WM Renewable Energy LLC, commissioned in 1992.

Facility nameplate · EIA Plant ID 50570Waste
Nameplate capacity
4.8 MW
Primary fuel
Waste
Commissioned
1992
Location
Anderson, Tennessee
Generation (2024)
31.1 GWh
Status
Operating
Technology
Landfill Gas
Units
5

Location

Map of the United States showing the location of Chestnut Ridge Gas Recovery

Anderson, Tennessee · 36.1172, -84.0317

Reported annual generation

YearGWh
201531.5
201633.9
201730.9
201829.8
201927.3
202031.9
202123.1
202222.3
202431.1

Nearby power plants

PlantFuelCapacityDistance
Norris DamHydroelectric131.4 MW~13 km
University of Tennessee Steam PlantNatural Gas5 MW~21 km
Buffalo MountainWind1.8 MW~28 km
Melton HillHydroelectric72 MW~35 km
Fort LoudounHydroelectric153.3 MW~41 km
Douglas DamHydroelectric150.8 MW~47 km