Crockett BESS

A 10 MW storage power plant in Harris, Texas, owned by Prologis Logistics Services Incorporated BESS, commissioned in 2024.

Facility nameplate · EIA Plant ID 68683Storage
Nameplate capacity
10 MW
Primary fuel
Storage
Commissioned
2024
Time in queue (20232025)
1.9 yrs
Owner
Prologis Logistics Services Incorporated BESS
Location
Harris, Texas
Generation (2024)
0 GWh
Status
Operating
Technology
Batteries
Units
1

This facility was matched to a ERCOT interconnection request (LBNL Queued Up): queued 2023, commercial operation 2025 1.9 years in the queue. See the ERCOT queue or typical durations.

Nearby power plants

PlantFuelCapacityDistance
WAL4526Natural Gas1.2 MW~6 km
Rice UniversityNatural Gas6.9 MW~6 km
The Methodist Hospital, Gas TurbineNatural Gas5 MW~8 km
TECO CHP-1Natural Gas98 MW~8 km
WAL5612Natural Gas1.2 MW~9 km
WAL3584Natural Gas1.2 MW~10 km

See all storage plants in Texas or browse all plants in Texas.