DD Fayetteville Solar NC LLC
A 23.1 MW solar power plant in Bladen, North Carolina, owned by Duke Energy Progress - (NC), commissioned in 2015.
Facility nameplate · EIA Plant ID 59117Solar
Nameplate capacity
23.1 MW
Primary fuel
Solar
Commissioned
2015
Time in queue (2012→2015)
3.3 yrs
Location
Bladen, North Carolina
Coordinates
Generation (2024)
37.9 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1
This facility was matched to a Non-ISO Southeast interconnection request (LBNL Queued Up): queued 2012, commercial operation 2015 — 3.3 years in the queue. See the Southeast queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2015 | 1 | |
| 2016 | 36 | |
| 2017 | 35.6 | |
| 2018 | 23.1 | |
| 2019 | 32.6 | |
| 2020 | 39.3 | |
| 2021 | 40.9 | |
| 2022 | 37.4 | |
| 2023 | 41.2 | |
| 2024 | 37.9 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Innovative Solar 42 | Solar | 71 MW | ~3 km |
| Robeson County LFG to Energy | Waste | 2 MW | ~8 km |
| Butler | Storage | 10 MW | ~9 km |
| Railroad Farm 2 | Solar | 5 MW | ~10 km |
| Smithfield Farmland Corp Bladen | Oil | 28.5 MW | ~10 km |
| Panda Solar NC 11, LLC | Solar | 2 MW | ~10 km |
See all solar plants in North Carolina or browse all plants in North Carolina.