Interconnection region
Non-ISO Southeast interconnection queue
1,067 proposed projects — 957 active and 110 suspended — are in the Non-ISO Southeast queue, totaling 161.38 GW of requested capacity. Projects that reached commercial operation here took a median of 3.8 years from interconnection request to online date (214 completed projects).
1,067
Proposed projects
161.38 GW
Requested capacity
Gas
Largest resource type
3.8 yrs
Median request → operation
Requested capacity by resource type
Gas 40.3%Solar 32.0%Battery 12.0%Solar + Battery 9.3%Nuclear 2.3%Other 2.1%Wind 1.6%Hydro 0.3%
By state in Non-ISO Southeast
Largest proposed projects in Non-ISO Southeast
| Type | ||||
|---|---|---|---|---|
| Smarr CC GI-193 | Gas | 2.00 GW | 2024 | 2028 |
| Queue 489 489 | Gas | 1.69 GW | 2021 | 2026 |
| Queue 977726 977726 | Gas | 1.62 GW | 2025 | — |
| Queue 628 628 | Gas | 1.60 GW | 2024 | 2030 |
| Queue 483 483 | Gas | 1.60 GW | 2021 | 2025 |
| Queue 620 620 | Gas | 1.60 GW | 2024 | 2031 |
| Duke Energy Progress, LLC project 958347 | Gas | 1.46 GW | 2024 | — |
| Queue 957264 957264 | Gas | 1.45 GW | 2024 | — |
| Queue 977731 977731 | Gas | 1.39 GW | 2025 | — |
| FPL project 107 | Nuclear | 1.30 GW | 2007 | 2027 |
| FPL project 108 | Nuclear | 1.30 GW | 2007 | 2028 |
| Queue IC-942susp. IC-942 | Solar + Battery | 1.20 GW | 2021 | 2025 |
| Queue 257 257 | Gas | 1.13 GW | 2014 | 2018 |
| Queue GI-83 GI-83 | Wind | 1.02 GW | 2019 | 2027 |
| Queue IC-1254a IC-1254a | Gas | 1.00 GW | 2024 | 2028 |
| Queue IC-1254b IC-1254b | Gas | 1.00 GW | 2024 | 2028 |
| Queue 977454 977454 | Gas | 990 MW | 2025 | — |
| Queue 283 283 | Gas | 819.4 MW | 2025 | 2029 |
| Queue 284 284 | Gas | 819.4 MW | 2025 | 2029 |
| Queue 285 285 | Gas | 819.4 MW | 2025 | 2029 |
| Queue 977564 977564 | Gas | 810 MW | 2025 | — |
| Queue 618 618 | Gas | 800 MW | 2024 | 2027 |
| Queue 622 622 | Gas | 800 MW | 2024 | 2031 |
| Queue LGE-GIS-2009-004 LGE-GIS-2009-004 | Gas | 785 MW | 2009 | 2010 |
| Queue 416 416 | Gas | 780 MW | 2020 | 2022 |
| Flint River 2 780 MW Unit GI-210 | Gas | 780 MW | 2025 | 2029 |
| Flint River 780 MW Unit GI-198 | Gas | 780 MW | 2024 | 2029 |
| Queue 417 417 | Gas | 780 MW | 2020 | 2022 |
| Queue 25-IC-1327 25-IC-1327 | Gas | 759.1 MW | 2025 | 2030 |
| Queue 25-IC-1329 25-IC-1329 | Gas | 759.1 MW | 2025 | 2030 |
| Queue 25-IC-1330 25-IC-1330 | Gas | 759.1 MW | 2025 | 2030 |
| Queue 25RSC-012 25RSC-012 | Gas | 752 MW | 2025 | 2031 |
| Queue IC-1255 IC-1255 | Gas | 722 MW | 2024 | 2028 |
| Queue IC-1256 IC-1256 | Gas | 722 MW | 2024 | 2029 |
| Queue IC-1257 IC-1257 | Gas | 722 MW | 2024 | 2029 |
| Queue IC-1258 IC-1258 | Gas | 722 MW | 2024 | 2029 |
| Queue IC-1259 IC-1259 | Gas | 722 MW | 2024 | 2029 |
| Queue IC-1260 IC-1260 | Gas | 722 MW | 2024 | 2031 |
| Queue IC-1263 IC-1263 | Gas | 722 MW | 2024 | 2028 |
| Queue IC-1264 IC-1264 | Gas | 722 MW | 2024 | 2029 |
| Queue 25-IC-1382 25-IC-1382 | Gas | 707 MW | 2025 | 2031 |
| Queue 25RSC-001 25RSC-001 | Gas | 691.6 MW | 2025 | 2031 |
| Queue LGE-GIS-2013-001 LGE-GIS-2013-001 | Gas | 691 MW | 2013 | 2015 |
| Queue LGE-GIS-2010-001 LGE-GIS-2010-001 | Gas | 690 MW | 2010 | 2015 |
| Queue IC-1158susp. IC-1158 | Gas | 685 MW | 2023 | 2028 |
| Queue LGE-CS2025-002 LGE-CS2025-002 | Gas | 680 MW | 2025 | 2031 |
| Queue LGE-GIS-2022-003 LGE-GIS-2022-003 | Gas | 660 MW | 2022 | 2027 |
| Queue LGE-GIS-2023-002 LGE-GIS-2023-002 | Gas | 660 MW | 2023 | 2030 |
| Queue JEA-Q008 JEA-Q008 | Gas | 645 MW | 2018 | 2030 |
| Queue 569 569 | Gas | 620 MW | 2023 | 2026 |
Showing the 50 largest of 1,067 projects by requested capacity.
Browse the national queue or read the queue insights.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).