Decatur Parkway Solar Project, LLC
A 80 MW solar power plant in Decatur, Georgia, owned by Southern Power Co, commissioned in 2015.
Facility nameplate · EIA Plant ID 59450Solar
Nameplate capacity
80 MW
Primary fuel
Solar
Commissioned
2015
Owner
Location
Decatur, Georgia
Coordinates
Generation (2024)
178.7 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1
Location
Decatur, Georgia · 30.9919, -84.6339
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2015 | 0.2 | |
| 2016 | 198.8 | |
| 2017 | 185.5 | |
| 2018 | 175.2 | |
| 2019 | 184.9 | |
| 2020 | 173.6 | |
| 2021 | 153.6 | |
| 2022 | 166.2 | |
| 2023 | 171.6 | |
| 2024 | 178.7 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Bainbridge Solar | Solar | 1 MW | ~3 km |
| Decatur County Solar Project | Solar | 20 MW | ~3 km |
| Walton Bainbridge Power Facility | Oil | 80 MW | ~12 km |
| BE Solar LLC | Solar | 3 MW | ~12 km |
| Decatur Solar | Solar | 200 MW | ~24 km |
| Cool Springs Solar (Hybrid) | Solar | 253 MW | ~27 km |
See all solar plants in Georgia or browse all plants in Georgia.