East Blackland Solar Project 1

A 144 MW solar power plant in Travis, Texas, owned by Duke Energy Renewables Services, commissioned in 2021.

Facility nameplate · EIA Plant ID 57659Solar
Nameplate capacity
144 MW
Primary fuel
Solar
Commissioned
2021
Time in queue (2015→2021)
6.3 yrs
Location
Travis, Texas
Generation (2024)
271.9 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1

This facility was matched to a ERCOT interconnection request (LBNL Queued Up): queued 2015, commercial operation 2021 — 6.3 years in the queue. See the ERCOT queue or typical durations.

Location

Map of the United States showing the location of East Blackland Solar Project 1

Travis, Texas · 30.4214, -97.4614

Reported annual generation

YearGWh
2021147.8
2022320.1
2023303.6
2024271.9

Nearby power plants

PlantFuelCapacityDistance
TX19 River Valley Storage 1Storage50 MW~10 km
TX21 River Valley Storage 2Storage50 MW~10 km
TX12 Silicon Hill StorageStorage100 MW~11 km
WAL5479Natural Gas1.2 MW~14 km
Austin Gas RecoveryWaste4.8 MW~18 km
WAL5480Natural Gas1.2 MW~19 km

See all solar plants in Texas or browse all plants in Texas.