Falfurrias BESS

A 9.9 MW storage power plant in Brooks, Texas, owned by HEN Infrastructure, L.L.C., commissioned in 2024.

Facility nameplate · EIA Plant ID 66792Storage
Nameplate capacity
9.9 MW
Primary fuel
Storage
Commissioned
2024
Time in queue (20232025)
1.6 yrs
Owner
HEN Infrastructure, L.L.C.
Location
Brooks, Texas
Generation (2024)
-0.1 GWh
Status
Operating
Technology
Batteries
Units
1

This facility was matched to a ERCOT interconnection request (LBNL Queued Up): queued 2023, commercial operation 2025 1.6 years in the queue. See the ERCOT queue or typical durations.

Nearby power plants

PlantFuelCapacityDistance
Alexis Solar, LLCSolar10 MW~40 km
Ticona Polymers IncNatural Gas44.2 MW~48 km
Baffin WindWind188 MW~54 km
Penascal II Wind Project LLCWind201.6 MW~59 km
WAL791Natural Gas1.2 MW~59 km
Stella Wind FarmWind201 MW~59 km

See all storage plants in Texas or browse all plants in Texas.