Greasewood II LLC

A 306 MW solar power plant in Pecos, Texas, owned by Greasewood II LLC, commissioned in 2024.

Facility nameplate · EIA Plant ID 67006Solar
Nameplate capacity
306 MW
Primary fuel
Solar
Commissioned
2024
Time in queue (20192024)
5.2 yrs
Owner
Greasewood II LLC
Location
Pecos, Texas
Generation (2024)
178.4 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1

This facility was matched to a ERCOT interconnection request (LBNL Queued Up): queued 2019, commercial operation 2024 5.2 years in the queue. See the ERCOT queue or typical durations.

Nearby power plants

PlantFuelCapacityDistance
Greasewood SolarSolar255 MW~14 km
Emerald GroveSolar108 MW~23 km
Woodward Mountain IWind82 MW~25 km
Woodward Mountain IIWind78 MW~25 km
Crossett Power Management LLCStorage203 MW~29 km
PavoStorage175 MW~30 km

See all solar plants in Texas or browse all plants in Texas.