Holstein 1 Solar Farm
A 200 MW solar power plant in Nolan, Texas, owned by Duke Energy Renewables Services, commissioned in 2020.
Facility nameplate · EIA Plant ID 61962Solar
Nameplate capacity
200 MW
Primary fuel
Solar
Commissioned
2020
Time in queue (2016→2020)
3.5 yrs
Owner
Duke Energy Renewables Services
Location
Nolan, Texas
Coordinates
Generation (2024)
382.1 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1
This facility was matched to a ERCOT interconnection request (LBNL Queued Up): queued 2016, commercial operation 2020 — 3.5 years in the queue. See the ERCOT queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2020 | 360.1 | |
| 2021 | 420.7 | |
| 2022 | 450.7 | |
| 2023 | 413.4 | |
| 2024 | 382.1 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Turkey Track Wind Energy LLC | Wind | 169.5 MW | ~14 km |
| Horse Hollow Wind Energy Center | Wind | 735.5 MW | ~16 km |
| Buffalo Gap 3 Wind Farm | Wind | 170.2 MW | ~21 km |
| Mesquite Star | Wind | 418.9 MW | ~22 km |
| Buffalo Gap 2 Wind Farm | Wind | 232.5 MW | ~24 km |
| Buffalo Gap Wind Farm | Wind | 120.6 MW | ~25 km |
See all solar plants in Texas or browse all plants in Texas.