Inertia Wind Project
A 301 MW wind power plant in Haskell, Texas, owned by Inertia Wind Project, LLC, commissioned in 2023.
Facility nameplate · EIA Plant ID 65546Wind
Nameplate capacity
301 MW
Primary fuel
Wind
Commissioned
2023
Time in queue (2020→2023)
3.4 yrs
Owner
Inertia Wind Project, LLC
Location
Haskell, Texas
Coordinates
Generation (2024)
1,247.5 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1
This facility was matched to a ERCOT interconnection request (LBNL Queued Up): queued 2020, commercial operation 2023 — 3.4 years in the queue. See the ERCOT queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2023 | 1,170.6 | |
| 2024 | 1,247.5 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| King Creek Wind Farm 1, LLC | Wind | 184 MW | ~15 km |
| OCI Alamo 7 LLC | Solar | 100 MW | ~17 km |
| Willow Springs Wind Farm | Wind | 250 MW | ~18 km |
| Azure Sky Solar | Solar | 316.2 MW | ~18 km |
| Horse Creek Wind Farm | Wind | 230 MW | ~19 km |
| King Creek Wind Farm 2, LLC | Wind | 209 MW | ~19 km |