Jumbo Hill Wind Project
A 160.7 MW wind power plant in Andrews, Texas, owned by Engie North America, commissioned in 2020.
Facility nameplate · EIA Plant ID 62630Wind
Nameplate capacity
160.7 MW
Primary fuel
Wind
Commissioned
2020
Time in queue (2016→2021)
4.9 yrs
Owner
Engie North America
Location
Andrews, Texas
Coordinates
Generation (2024)
593.8 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1
This facility was matched to a ERCOT interconnection request (LBNL Queued Up): queued 2016, commercial operation 2021 — 4.9 years in the queue. See the ERCOT queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2020 | 479.5 | |
| 2021 | 596.1 | |
| 2022 | 615.1 | |
| 2023 | 593 | |
| 2024 | 593.8 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Prospero Solar | Solar | 300 MW | ~15 km |
| Frankel | Oil | 9 MW | ~16 km |
| Prospero Solar II | Solar | 250 MW | ~16 km |
| Lapetus | Solar | 100 MW | ~27 km |
| SPS2 Jal | Solar | 10 MW | ~31 km |
| SPS1 Dollarhide | Solar | 10 MW | ~34 km |
See all wind plants in Texas or browse all plants in Texas.