Locust Ridge II LLC

A 102 MW wind power plant in Schuylkill, Pennsylvania, owned by Avangrid Power LLC, commissioned in 2009.

Facility nameplate · EIA Plant ID 56770Wind
Nameplate capacity
102 MW
Primary fuel
Wind
Commissioned
2009
Time in queue (20062009)
3.1 yrs
Owner
Avangrid Power LLC
Location
Schuylkill, Pennsylvania
Generation (2024)
184.1 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1

This facility was matched to a PJM Interconnection interconnection request (LBNL Queued Up): queued 2006, commercial operation 2009 3.1 years in the queue. See the PJM queue or typical durations.

Reported annual generation

YearGWh
2015212.6
2016216.7
2017211.9
2018217.8
2019199.8
2020201.8
2021190.3
2022206
2023187.8
2024184.1

Nearby power plants

PlantFuelCapacityDistance
St Nicholas Cogen ProjectCoal99.2 MW~3 km
Locust RidgeWind26 MW~3 km
John B Rich Memorial Power StationCoal88.4 MW~7 km
HazeltonNatural Gas171.5 MW~14 km
Romark PA SolarSolar1.8 MW~14 km
Hazle SpindleStorage20 MW~15 km

See all wind plants in Pennsylvania or browse all plants in Pennsylvania.