NJ Oak Solar Plant

A 10 MW solar power plant in Cumberland, New Jersey, owned by NJR Clean Energy Ventures Corporation, commissioned in 2011.

Facility nameplate · EIA Plant ID 57948Solar
Nameplate capacity
10 MW
Primary fuel
Solar
Commissioned
2011
Time in queue (20092011)
2 yrs
Location
Cumberland, New Jersey
Generation (2024)
17.2 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1

This facility was matched to a PJM Interconnection interconnection request (LBNL Queued Up): queued 2009, commercial operation 2011 2 years in the queue. See the PJM queue or typical durations.

Location

Map of the United States showing the location of NJ Oak Solar Plant

Cumberland, New Jersey · 39.3806, -75.1883

Reported annual generation

YearGWh
201515.9
201616
201715.2
201813.8
201914.6
202013.2
202116.7
202215.2
202315.4
202417.2

Nearby power plants

PlantFuelCapacityDistance
KDC Solar ASGMSolar3.8 MW~4 km
CCUA SolarSolar1.5 MW~6 km
Love Lane SolarSolar1.8 MW~10 km
Cumberland County Solid Waste ComplexWaste4.8 MW~11 km
Seabrook Solar PlantSolar6.8 MW~12 km
Millville City Sewer Auth WTPSolar1.2 MW~13 km