North Bend Wind Project, LLC
A 200 MW wind power plant in Hyde, South Dakota, owned by North Bend Wind Project, LLC, commissioned in 2023.
Facility nameplate · EIA Plant ID 67002Wind
Nameplate capacity
200 MW
Primary fuel
Wind
Commissioned
2023
Time in queue (2016→2024)
7.2 yrs
Owner
North Bend Wind Project, LLC
Location
Hyde, South Dakota
Coordinates
Generation (2024)
753.8 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1
This facility was matched to a SPP interconnection request (LBNL Queued Up): queued 2016, commercial operation 2024 — 7.2 years in the queue. See the SPP queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2023 | 37.8 | |
| 2024 | 753.8 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Triple H Wind Project | Wind | 250.2 MW | ~5 km |
| South Dakota Wind Energy Cente | Wind | 40.5 MW | ~23 km |
| Big Bend Dam | Hydroelectric | 538.3 MW | ~41 km |
| Rolling Thunder Wind Farm Hybrid | Wind | 25.8 MW | ~43 km |
| Pierre Solar | Solar | 1 MW | ~51 km |
| Ft. Pierre | Oil | 6 MW | ~57 km |
See all wind plants in South Dakota or browse all plants in South Dakota.