Triple H Wind Project
A 250.2 MW wind power plant in Hyde, South Dakota, owned by Engie North America, commissioned in 2020.
Facility nameplate · EIA Plant ID 63103Wind
Nameplate capacity
250.2 MW
Primary fuel
Wind
Commissioned
2020
Time in queue (2016→2020)
4.7 yrs
Owner
Engie North America
Location
Hyde, South Dakota
Coordinates
Generation (2024)
968.3 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1
This facility was matched to a SPP interconnection request (LBNL Queued Up): queued 2016, commercial operation 2020 — 4.7 years in the queue. See the SPP queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2020 | 119.2 | |
| 2021 | 1,028 | |
| 2022 | 1,018.7 | |
| 2023 | 918.4 | |
| 2024 | 968.3 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| North Bend Wind Project, LLC | Wind | 200 MW | ~5 km |
| South Dakota Wind Energy Cente | Wind | 40.5 MW | ~18 km |
| Rolling Thunder Wind Farm Hybrid | Wind | 25.8 MW | ~38 km |
| Big Bend Dam | Hydroelectric | 538.3 MW | ~42 km |
| Pierre Solar | Solar | 1 MW | ~56 km |
| Ft. Pierre | Oil | 6 MW | ~62 km |
See all wind plants in South Dakota or browse all plants in South Dakota.