A 106 MW wind power plant in Lewis, New York, owned by Invenergy Services LLC, commissioned in 2023.

Facility nameplate · EIA Plant ID 65522Wind
Nameplate capacity
106 MW
Primary fuel
Wind
Commissioned
2023
Time in queue (2016→2023)
7.6 yrs
Location
Lewis, New York
Generation (2024)
272.6 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1

This facility was matched to a NYISO interconnection request (LBNL Queued Up): queued 2016, commercial operation 2023 — 7.6 years in the queue. See the NYISO queue or typical durations.

Location

Map of the United States showing the location of Number Three Wind Project

Lewis, New York · 43.8396, -75.5699

Reported annual generation

YearGWh
2023137.7
2024272.6

Nearby power plants

PlantFuelCapacityDistance
Maple Ridge Wind FarmWind321.2 MW~6 km
Chambers 3 - Lewis CountySolar2 MW~9 km
Copenhagen PlantHydroelectric3.3 MW~10 km
Kings Falls HydroelectricHydroelectric1.6 MW~10 km
CH Resources Beaver FallsNatural Gas107.8 MW~12 km
Lower Beaver Falls ProjectHydroelectric1 MW~12 km