Summit Associates
A 1.9 MW solar power plant in Middlesex, New Jersey, owned by Public Service Elec & Gas Co, commissioned in 2011.
Facility nameplate · EIA Plant ID 57726Solar
Nameplate capacity
1.9 MW
Primary fuel
Solar
Commissioned
2011
Time in queue (2011→2011)
0.4 yrs
Owner
Public Service Elec & Gas Co
Location
Middlesex, New Jersey
Coordinates
Generation (2024)
1.6 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1
This facility was matched to a PJM Interconnection interconnection request (LBNL Queued Up): queued 2011, commercial operation 2011 — 0.4 years in the queue. See the PJM queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2015 | 2.6 | |
| 2016 | 2.6 | |
| 2017 | 2.4 | |
| 2018 | 2.2 | |
| 2019 | 2.5 | |
| 2020 | 2.6 | |
| 2021 | 2.4 | |
| 2022 | 2.5 | |
| 2023 | 2.2 | |
| 2024 | 1.6 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| 180 Raritan Solar | Solar | 1.9 MW | ~2 km |
| DG Iron Mountain | Solar | 5.4 MW | ~2 km |
| Wakefern Food Corp | Solar | 2 MW | ~2 km |
| FedEx Woodbridge | Solar | 2 MW | ~3 km |
| Sayreville | Oil | 212 MW | ~3 km |
| Heller 400M | Solar | 1.2 MW | ~3 km |
See all solar plants in New Jersey or browse all plants in New Jersey.