Summit - Cicero
A 5 MW solar power plant in Onondaga, New York, owned by MN8 Energy LLC, commissioned in 2024.
Facility nameplate · EIA Plant ID 66273Solar
Nameplate capacity
5 MW
Primary fuel
Solar
Commissioned
2024
Owner
MN8 Energy LLC
Location
Onondaga, New York
Coordinates
Generation (2024)
6.9 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1