Trailside Solar Center

A 74.5 MW solar power plant in St Johns, Florida, owned by Florida Power & Light Co, commissioned in 2020.

Facility nameplate · EIA Plant ID 62916Solar
Nameplate capacity
74.5 MW
Primary fuel
Solar
Commissioned
2020
Time in queue (20172020)
3.5 yrs
Owner
Florida Power & Light Co
Location
St Johns, Florida
Coordinates
Generation (2024)
132.8 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1

This facility was matched to a Non-ISO Southeast interconnection request (LBNL Queued Up): queued 2017, commercial operation 2020 3.5 years in the queue. See the Southeast queue or typical durations.

Reported annual generation

YearGWh
20208.1
2021150.4
2022153.5
2023144.7
2024132.8

Nearby power plants

PlantFuelCapacityDistance
Seminole (FL)Natural Gas1.90 GW~20 km
Tupelo SolarSolar74.5 MW~21 km
Rice CreekSolar74.9 MW~26 km
Georgia-Pacific Palatka OperationsBiomass79.8 MW~27 km
Anhinga Solar Energy CenterSolar74.5 MW~27 km
Magnolia Springs Solar CenterSolar74.5 MW~29 km

See all solar plants in Florida or browse all plants in Florida.