Twin Rivers Solar Power Plant
A 74.9 MW solar power plant in Hamilton, Florida, owned by Duke Energy Florida, LLC, commissioned in 2021.
Facility nameplate · EIA Plant ID 63518Solar
Nameplate capacity
74.9 MW
Primary fuel
Solar
Commissioned
2021
Time in queue (2016→2021)
4.4 yrs
Owner
Duke Energy Florida, LLC
Location
Hamilton, Florida
Coordinates
Generation (2024)
156.6 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1
This facility was matched to a Non-ISO Southeast interconnection request (LBNL Queued Up): queued 2016, commercial operation 2021 — 4.4 years in the queue. See the Southeast queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2021 | 85 | |
| 2022 | 166.2 | |
| 2023 | 147.2 | |
| 2024 | 156.6 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Swift Creek Chemical Complex | Other | 18.8 MW | ~10 km |
| Jennings Energy Storage Facility | Storage | 5.5 MW | ~20 km |
| Hamilton Solar Power Plant | Solar | 74.9 MW | ~21 km |
| Echo River Solar | Solar | 104.5 MW | ~21 km |
| Suwannee Solar Facility | Solar | 8.8 MW | ~22 km |
| Falmouth Renewable Energy Center | Solar | 74.9 MW | ~23 km |
See all solar plants in Florida or browse all plants in Florida.