Wagyu
A 120 MW solar power plant in Brazoria, Texas, owned by Cubico USA, LLC, commissioned in 2020.
Facility nameplate · EIA Plant ID 63273Solar
Nameplate capacity
120 MW
Primary fuel
Solar
Commissioned
2020
Time in queue (2017→2021)
4.6 yrs
Owner
Cubico USA, LLC
Location
Brazoria, Texas
Coordinates
Generation (2024)
208.3 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1
This facility was matched to a ERCOT interconnection request (LBNL Queued Up): queued 2017, commercial operation 2021 — 4.6 years in the queue. See the ERCOT queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2020 | 119.9 | |
| 2021 | 229.8 | |
| 2022 | 236.6 | |
| 2023 | 192 | |
| 2024 | 208.3 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Brazoria West | Solar | 200 MW | ~6 km |
| TX23 Roughneck Storage | Storage | 50 MW | ~9 km |
| Prospect Storage | Storage | 9.9 MW | ~10 km |
| Second Division Solar | Solar | 100 MW | ~11 km |
| Brazoria County Solar Project (Danciger) | Solar | 200 MW | ~12 km |
| Fighting Jays Solar Project | Solar | 227.5 MW | ~15 km |
See all solar plants in Texas or browse all plants in Texas.