A 19.8 MW solar power plant in Tulare, California, owned by Consolidated Edison Development Inc., commissioned in 2014.
Facility nameplate · EIA Plant ID 58973Solar
Nameplate capacity
19.8 MW
Primary fuel
Solar
Commissioned
2014
Time in queue (2010→2014)
4.7 yrs
Owner
Consolidated Edison Development Inc.
Location
Tulare, California
Coordinates
Generation (2024)
48.4 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1
This facility was matched to a CAISO interconnection request (LBNL Queued Up): queued 2010, commercial operation 2014 — 4.7 years in the queue. See the CAISO queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2015 | 53.1 | |
| 2016 | 52.9 | |
| 2017 | 51.2 | |
| 2018 | 49.7 | |
| 2019 | 49.9 | |
| 2020 | 49.3 | |
| 2021 | 50 | |
| 2022 | 52.2 | |
| 2023 | 49.3 | |
| 2024 | 48.4 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| CED Ducor 1 | Solar | 20 MW | ~3 km |
| CED Ducor 4 | Solar | 20 MW | ~3 km |
| CED Ducor 3 | Solar | 15 MW | ~3 km |
| CED Ducor 2 | Solar | 20 MW | ~4 km |
| Nicolis Solar PV Plant | Solar | 20 MW | ~4 km |