Wistaria Ranch Solar

A 106.7 MW solar power plant in Imperial, California, owned by Consolidated Edison Development Inc., commissioned in 2018.

Facility nameplate · EIA Plant ID 61750Solar
Nameplate capacity
106.7 MW
Primary fuel
Solar
Commissioned
2018
Time in queue (2008→2018)
10.4 yrs
Location
Imperial, California
Coordinates
Generation (2024)
291.9 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1

This facility was matched to a CAISO interconnection request (LBNL Queued Up): queued 2008, commercial operation 2018 — 10.4 years in the queue. See the CAISO queue or typical durations.

Location

Map of the United States showing the location of Wistaria Ranch Solar

Imperial, California · 32.676, -115.619

Reported annual generation

YearGWh
201815.4
2019292.6
2020269.8
2021258.8
2022252.8
2023273.1
2024291.9

Nearby power plants

PlantFuelCapacityDistance
Mount Signal Solar Farm IISolar153.5 MW~1 km
Centinela Solar EnergySolar174.8 MW~3 km
Imperial Valley Solar, LLCSolar199.9 MW~3 km
Imperial Solar Energy Center SouthSolar128.9 MW~4 km
Drew Solar LLCSolar100 MW~5 km
LeConte Energy StorageStorage125 MW~5 km

See all solar plants in California or browse all plants in California.