Wye Mills VNEM CSG
A 10 MW solar power plant in Queen Annes, Maryland, owned by Tesla Inc., commissioned in 2016.
Facility nameplate · EIA Plant ID 60604Solar
Nameplate capacity
10 MW
Primary fuel
Solar
Commissioned
2016
Time in queue (2012→2016)
4.3 yrs
Owner
Tesla Inc.
Location
Queen Annes, Maryland
Coordinates
Generation (2024)
18.5 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1
This facility was matched to a PJM Interconnection interconnection request (LBNL Queued Up): queued 2012, commercial operation 2016 — 4.3 years in the queue. See the PJM queue or typical durations.
Reported annual generation
| Year | GWh | |
|---|---|---|
| 2016 | 2.1 | |
| 2017 | 20.6 | |
| 2018 | 17.9 | |
| 2019 | 18 | |
| 2020 | 15 | |
| 2021 | 19 | |
| 2022 | 19.7 | |
| 2023 | 18.9 | |
| 2024 | 18.5 |
Nearby power plants
| Plant | Fuel | Capacity | Distance |
|---|---|---|---|
| Chesapeake College | Solar | 1.5 MW | ~4 km |
| Queen Anne's County | Solar | 2 MW | ~10 km |
| Bd of Educ of Queen Anne's Cnty, Cnty HS | Solar | 1.7 MW | ~11 km |
| Easton 2 | Oil | 38.8 MW | ~16 km |
| Easton | Oil | 31.1 MW | ~18 km |
| Church Hill | Solar | 6 MW | ~19 km |
See all solar plants in Maryland or browse all plants in Maryland.