State queue · Arkansas
Arkansas interconnection queue
131 proposed generation and storage projects — 131 active and 0 suspended — are in Arkansas's interconnection queue, primarily in the MISO, totaling 30.18 GW of requested capacity. Solar leads with 18.19 GW.
131
Proposed projects
30.18 GW
Requested capacity
Solar
Largest resource type
2026
Median planned online year
Requested capacity by resource type
Solar 60.3%Solar + Battery 18.7%Wind 9.8%Gas 5.4%Battery 5.1%Other 0.7%
Proposed projects by resource type
Solar projects81 · 18.19 GWSolar + Battery projects26 · 5.66 GWWind projects12 · 2.95 GWBattery projects8 · 1.54 GW
Also in the queue (too few for a dedicated page): Gas (3), Other (1).
All proposed projects in Arkansas
| Type | ||||
|---|---|---|---|---|
| Queue J3829 J3829 | Gas | 770 MW | 2024 | 2028 |
| Queue J3874 J3874 | Gas | 770 MW | 2024 | 2028 |
| Queue J2261 J2261 | Solar | 625 MW | 2021 | 2028 |
| Queue J2262 J2262 | Solar | 625 MW | 2021 | 2028 |
| Queue J2477 J2477 | Solar | 600 MW | 2022 | 2026 |
| Queue J2478 J2478 | Solar | 550 MW | 2022 | 2026 |
| Queue J1060 J1060 | Solar | 500 MW | 2018 | 2023 |
| Queue J1855 J1855 | Solar | 500 MW | 2021 | 2026 |
| Queue J1897 J1897 | Solar + Battery | 500 MW | 2021 | 2027 |
| Queue J1899 J1899 | Solar + Battery | 500 MW | 2021 | 2027 |
| Queue J2190 J2190 | Solar + Battery | 500 MW | 2021 | 2027 |
| Queue J2395 J2395 | Solar | 500 MW | 2022 | 2025 |
| Queue J2696 J2696 | Solar | 500 MW | 2022 | 2027 |
| Queue J2841 J2841 | Wind | 500 MW | 2022 | 2025 |
| Queue J3192 J3192 | Solar | 500 MW | 2022 | 2025 |
| Queue J3401 J3401 | Solar | 500 MW | 2024 | 2028 |
| Queue J4082 J4082 | Battery | 500 MW | 2025 | 2030 |
| Queue J3030 J3030 | Solar + Battery | 450 MW | 2022 | 2027 |
| Queue J1858 J1858 | Solar | 440 MW | 2021 | 2028 |
| Queue J2088 J2088 | Solar | 400 MW | 2022 | 2027 |
| Queue J2396 J2396 | Solar | 400 MW | 2022 | 2025 |
| Queue J2907 J2907 | Solar + Battery | 400 MW | 2022 | 2026 |
| Queue S1125 S1125 | Solar + Battery | 400 MW | 2025 | 2028 |
| Queue J2864 J2864 | Solar | 375 MW | 2022 | 2027 |
| Queue J2865 J2865 | Solar | 375 MW | 2022 | 2027 |
| Queue J2866 J2866 | Solar | 375 MW | 2022 | 2027 |
| Queue J3597 J3597 | Wind | 348 MW | 2024 | 2028 |
| Queue J4088 J4088 | Solar + Battery | 340 MW | 2025 | 2028 |
| Queue J3982 J3982 | Wind | 319.5 MW | 2024 | 2030 |
| Queue J1710 J1710 | Solar | 300 MW | 2020 | 2026 |
| Queue J2482 J2482 | Solar | 300 MW | 2022 | 2026 |
| Queue J2613 J2613 | Wind | 300 MW | 2022 | 2025 |
| Queue J3131 J3131 | Solar | 300 MW | 2022 | 2026 |
| Queue J3040 J3040 | Solar | 290 MW | 2022 | 2027 |
| Queue J1415 J1415 | Solar | 250 MW | 2019 | 2024 |
| Queue J1872 J1872 | Solar | 250 MW | 2021 | 2028 |
| Queue J1873 J1873 | Solar | 250 MW | 2021 | 2028 |
| Queue J2143 J2143 | Solar | 250 MW | 2021 | 2027 |
| Queue J2294 J2294 | Solar | 250 MW | 2021 | 2028 |
| Queue J2523 J2523 | Solar | 250 MW | 2022 | 2026 |
| Queue J2924 J2924 | Solar + Battery | 222 MW | 2022 | 2027 |
| Queue J3457 J3457 | Solar | 215 MW | 2024 | 2027 |
| Queue GEN-2021-033 GEN-2021-033 | Solar | 204.1 MW | 2021 | 2028 |
| Queue GEN-2021-036 GEN-2021-036 | Solar | 204.1 MW | 2021 | 2027 |
| Queue J1007 J1007 | Solar | 200 MW | 2018 | 2023 |
| Queue J1215 J1215 | Solar | 200 MW | 2019 | 2024 |
| Queue J1558 J1558 | Solar | 200 MW | 2020 | 2026 |
| Queue J1559 J1559 | Solar | 200 MW | 2020 | 2026 |
| Queue J1562 J1562 | Solar | 200 MW | 2020 | 2025 |
| Queue J2089 J2089 | Solar | 200 MW | 2021 | 2027 |
| Queue J2153 J2153 | Solar + Battery | 200 MW | 2021 | 2027 |
| Queue J2181 J2181 | Solar | 200 MW | 2022 | 2027 |
| Queue J2298 J2298 | Solar | 200 MW | 2021 | 2028 |
| Queue J2351 J2351 | Solar | 200 MW | 2022 | 2026 |
| Queue J2577 J2577 | Wind | 200 MW | 2022 | 2025 |
| Queue J2641 J2641 | Wind | 200 MW | 2022 | 2025 |
| Queue J3058 J3058 | Solar + Battery | 200 MW | 2025 | 2025 |
| Queue J3090 J3090 | Solar | 200 MW | 2022 | 2025 |
| Queue J3120 J3120 | Solar + Battery | 200 MW | 2022 | 2026 |
| Queue J3122 J3122 | Wind | 200 MW | 2022 | 2025 |
| Queue J3230 J3230 | Wind | 200 MW | 2022 | 2025 |
| Queue J3449 J3449 | Solar | 200 MW | 2024 | 2028 |
| Queue J934 J934 | Solar | 200 MW | 2017 | 2022 |
| Queue GEN-2022-130 GEN-2022-130 | Battery | 200 MW | 2023 | 2030 |
| Surplus; J1434 S1101 | Battery | 200 MW | 2025 | 2027 |
| Surplus; J1562 S1100 | Battery | 200 MW | 2025 | 2027 |
| Surplus; J834 S1074 | Other | 200 MW | 2025 | 2027 |
| Queue J2750 J2750 | Solar | 197.5 MW | 2025 | 2026 |
| Queue J3292 J3292 | Wind | 193 MW | 2024 | 2028 |
| Queue J2237 J2237 | Solar | 185 MW | 2021 | 2027 |
| Queue J1437 J1437 | Wind | 180 MW | 2019 | 2024 |
| Queue J919 J919 | Solar | 180 MW | 2017 | 2022 |
| Surplus; J1007 S1094 | Battery | 180 MW | 2025 | 2026 |
| Queue J2437 J2437 | Wind | 175 MW | 2022 | 2027 |
| Queue J586 J586 | Solar | 175 MW | 2016 | 2021 |
| Queue J2759 J2759 | Solar | 170 MW | 2023 | 2029 |
| Queue J2397 J2397 | Solar + Battery | 160 MW | 2022 | 2025 |
| Queue J1155 J1155 | Solar | 150 MW | 2018 | 2022 |
| Queue J1856 J1856 | Solar | 150 MW | 2021 | 2026 |
| Queue J2734 J2734 | Solar + Battery | 150 MW | 2025 | 2025 |
| Queue J2764 J2764 | Solar + Battery | 150 MW | 2025 | 2025 |
| Queue J2880 J2880 | Solar + Battery | 150 MW | 2022 | 2026 |
| Queue J2955 J2955 | Solar | 150 MW | 2023 | 2026 |
| Queue J3619 J3619 | Solar | 150 MW | 2024 | 2028 |
| Queue ERAS-2025-005 ERAS-2025-005 | Solar + Battery | 150 MW | 2025 | 2029 |
| Queue GEN-2023-132 GEN-2023-132 | Solar | 150 MW | 2023 | 2028 |
| Queue J2901 J2901 | Solar | 140 MW | 2022 | 2027 |
| Queue J2983 J2983 | Solar | 140 MW | 2022 | 2025 |
| Queue J4174 J4174 | Battery | 140 MW | 2025 | 2030 |
| Queue J1125 J1125 | Solar | 135 MW | 2018 | 2023 |
| Queue J1816 J1816 | Solar | 135 MW | 2022 | 2025 |
| Queue J1842 J1842 | Wind | 135 MW | 2021 | 2024 |
| Queue J2985 J2985 | Solar | 135 MW | 2022 | 2025 |
| Queue J2801 J2801 | Solar | 130 MW | 2023 | 2026 |
| Queue J2818 J2818 | Solar + Battery | 130 MW | 2025 | 2025 |
| Queue J2881 J2881 | Solar | 125 MW | 2022 | 2026 |
| Queue J3109 J3109 | Solar + Battery | 120 MW | 2022 | 2026 |
| Queue J2350 J2350 | Solar | 115.5 MW | 2022 | 2025 |
| Queue J2634 J2634 | Solar | 105.8 MW | 2022 | 2025 |
| Queue J2639 J2639 | Solar | 105.8 MW | 2022 | 2025 |
Showing the 100 largest of 131 projects by requested capacity.
See 112 operating plants in Arkansas · Regions: MISO, SPP.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition). Data: LBNL backbone through December 31, 2025; ISO-region statuses refreshed monthly (last: July 2026); non-ISO West and Southeast as of the LBNL edition.