California · Gas
Proposed gas projects in California
There are 9 proposed gas projects in California's interconnection queue, totaling 2.25 GW of requested capacity. The largest is SUNRISE POWER IMPROVEMENT at 655.7 MW, and the median planned online year is 2027.
9
Proposed projects
2.25 GW
Requested capacity
249.7 MW
Average project size
2027
Median planned online year
All proposed gas projects in California
| Type | ||||
|---|---|---|---|---|
| SUNRISE POWER IMPROVEMENT 1745 | Gas | 655.7 MW | 2020 | 2024 |
| Aviation 2349 | Gas | 600 MW | 2023 | 2028 |
| Duran 2351 | Gas | 300 MW | 2023 | 2028 |
| Comstock 2339 | Gas | 199 MW | 2023 | 2028 |
| TRACY COMBINED-CYCLE POWER PLANT 268 | Gas | 145 MW | 2007 | 2027 |
| LOS ESTEROS CRITICAL ENERGY FACILITY EXPANSION 378 | Gas | 120 MW | 2008 | 2023 |
| MIDWAY PEAKING 54 | Gas | 119.9 MW | 2005 | 2027 |
| FRESNO COGENERATION EXPANSION PROJECT 61 | Gas | 73.3 MW | 2005 | 2023 |
| Queue GI-2025-179 GI-2025-179 | Gas | 34.8 MW | 2025 | 2027 |
Browse California's full interconnection queue. Compare with operating capacity: 314 operating natural gas plants in California. Nationwide: Natural Gas plants nationwide.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).