California · Solar + Battery
Proposed solar + battery projects in California
There are 196 proposed solar + battery projects in California's interconnection queue, totaling 58.76 GW of requested capacity. The largest is Queue Q92 at 1.65 GW, and the median planned online year is 2028.
196
Proposed projects
58.76 GW
Requested capacity
299.8 MW
Average project size
2028
Median planned online year
All proposed solar + battery projects in California
| Type | ||||
|---|---|---|---|---|
| Queue Q92 Q92 | Solar + Battery | 1.65 GW | 2022 | 2025 |
| Queue Q98 Q98 | Solar + Battery | 1.50 GW | 2023 | 2030 |
| Queue Q68 Q68 | Solar + Battery | 1.20 GW | 2019 | 2022 |
| DARDEN 1949 | Solar + Battery | 1.18 GW | 2021 | 2028 |
| UMBRIEL 2166 | Solar + Battery | 1.18 GW | 2021 | 2035 |
| WINGTIP SOLAR 1 1943 | Solar + Battery | 1.18 GW | 2021 | 2032 |
| Muon 2266 | Solar + Battery | 1.17 GW | 2023 | 2028 |
| ANGELENO SOLAR FARM 1625 | Solar + Battery | 1.15 GW | 2019 | 2028 |
| PLUM 1968 | Solar + Battery | 1.04 GW | 2021 | 2031 |
| Queue Q96 Q96 | Solar + Battery | 1.00 GW | 2023 | 2030 |
| Queue Q97 Q97 | Solar + Battery | 1.00 GW | 2023 | 2030 |
| Ripple 2234 | Solar + Battery | 945.9 MW | 2023 | 2031 |
| Quark 2267 | Solar + Battery | 869.4 MW | 2023 | 2028 |
| BUTTONBUSH SOLAR HYBRID ENERGY CENTER 1596 | Solar + Battery | 818 MW | 2019 | 2026 |
| Broadview 2308 | Solar + Battery | 816.4 MW | 2023 | 2028 |
| Queue GI-2022-164 GI-2022-164 | Solar + Battery | 800 MW | 2022 | 2026 |
| Queue 2023-G1 2023-G1 | Solar + Battery | 800 MW | 2023 | 2028 |
| Queue 2023-G2 2023-G2 | Solar + Battery | 800 MW | 2023 | 2028 |
| SANBORN HYBRID 3 1632 | Solar + Battery | 764.9 MW | 2019 | 2026 |
| Sunflower 2240 | Solar + Battery | 715.1 MW | 2023 | 2031 |
| EUISMOD 2055 | Solar + Battery | 623.5 MW | 2021 | 2028 |
| Sunvine 2319 | Solar + Battery | 613.7 MW | 2023 | 2031 |
| Solstice B 2254 | Solar + Battery | 606.4 MW | 2023 | 2031 |
| SILVER RIDGE MOUNT SIGNAL 124 | Solar + Battery | 600 MW | 2006 | 2027 |
| Solstice A 2252 | Solar + Battery | 556 MW | 2023 | 2031 |
| Queue 20 20 | Solar + Battery | 550 MW | 2022 | 2029 |
| Musketeers 2312 | Solar + Battery | 524.5 MW | 2023 | 2029 |
| OBERON 1642 | Solar + Battery | 518.4 MW | 2019 | 2026 |
| DESCENDANT RANCH 1 1496 | Solar + Battery | 513.5 MW | 2018 | 2034 |
| GRACE ENERGY CENTER 1761 | Solar + Battery | 508.6 MW | 2020 | 2027 |
| SUNBAKED SOLAR 2149 | Solar + Battery | 508.6 MW | 2021 | 2029 |
| Queue GI-2023-167 GI-2023-167 | Solar + Battery | 500 MW | 2023 | 2026 |
| BELLEFIELD 2 SOLAR FARM 1631 | Solar + Battery | 500 MW | 2019 | 2024 |
| BELLEFIELD SOLAR FARM 1510 | Solar + Battery | 500 MW | 2018 | 2025 |
| PELICANS JAW HYBRID SOLAR 1593 | Solar + Battery | 500 MW | 2019 | 2028 |
| SOLSKEN 2085 | Solar + Battery | 464.4 MW | 2021 | 2033 |
| ATHOS POWER PLANT 1405 | Solar + Battery | 458 MW | 2017 | 2027 |
| INVICTUS 2045 | Solar + Battery | 430.2 MW | 2021 | 2029 |
| ANTELOPE SOLAR 2 1208 | Solar + Battery | 423 MW | 2015 | 2025 |
| Amanece 2328 | Solar + Battery | 419 MW | 2023 | 2029 |
| Carissalito Creek 2370 | Solar + Battery | 415.9 MW | 2023 | 2030 |
| ARTEMIS 1980 | Solar + Battery | 412.3 MW | 2021 | 2029 |
| POTENTIA-VIRIDI 1702 | Solar + Battery | 410 MW | 2020 | 2028 |
| VALLEY SUNLIGHT REFINERY 2004 | Solar + Battery | 410 MW | 2021 | 2032 |
| Maravillosa 2 2361 | Solar + Battery | 407.2 MW | 2023 | 2029 |
| MATTERHORN 2366 | Solar + Battery | 404.9 MW | 2023 | 2029 |
| Queue Q76 Q76 | Solar + Battery | 400 MW | 2020 | 2023 |
| CALYPSO SOLAR 1636 | Solar + Battery | 400 MW | 2019 | 2031 |
| LYCAN SOLAR 1643 | Solar + Battery | 400 MW | 2019 | 2030 |
| SCARLET 1135 | Solar + Battery | 400 MW | 2015 | 2025 |
| Stable 2250 | Solar + Battery | 376.8 MW | 2023 | 2031 |
| SOLEIL CANTIL 2078 | Solar + Battery | 372.3 MW | 2021 | 2033 |
| Sunglow 2260 | Solar + Battery | 372.2 MW | 2023 | 2030 |
| East Wonder 2342 | Solar + Battery | 366.9 MW | 2023 | 2029 |
| KINGSLEY SOLAR FARM 1665 | Solar + Battery | 360 MW | 2019 | 2030 |
| BUTTONBUSH SOLAR 2 1987 | Solar + Battery | 358.2 MW | 2021 | 2032 |
| PRESIDIO 1887 | Solar + Battery | 356.6 MW | 2021 | 2030 |
| Queue Q80 Q80 | Solar + Battery | 350 MW | 2021 | 2024 |
| Queue 8 8 | Solar + Battery | 344 MW | 2021 | 2026 |
| SANBORN SOLAR 2 1518 | Solar + Battery | 334 MW | 2018 | 2025 |
| BIG SKY SOLAR 768 | Solar + Battery | 320 MW | 2011 | 2023 |
| DAGGETT SOLAR 3 1314 | Solar + Battery | 313.9 MW | 2016 | 2023 |
| CADY SOLAR 2103 | Solar + Battery | 313 MW | 2021 | 2031 |
| DAYLIGHT 1223 | Solar + Battery | 310.7 MW | 2016 | 2028 |
| CHERRY LANE HYBRID 2015 | Solar + Battery | 310.6 MW | 2021 | 2031 |
| MidBishop 2362 | Solar + Battery | 307.8 MW | 2023 | 2029 |
| AUSTRALIS 1952 | Solar + Battery | 307 MW | 2021 | 2031 |
| Blue Star 2298 | Solar + Battery | 306.4 MW | 2023 | 2029 |
| Maestro 2356 | Solar + Battery | 304.7 MW | 2023 | 2029 |
| Brown Bear 2336 | Solar + Battery | 303.8 MW | 2023 | 2029 |
| CORNUCOPIA HYBRID 1959 | Solar + Battery | 303.7 MW | 2021 | 2030 |
| Queue 2019-G1 2019-G1 | Solar + Battery | 300 MW | 2019 | 2027 |
| ROSAMOND WEST SOLAR 506 | Solar + Battery | 299.6 MW | 2009 | 2029 |
| EASLEY 2042 | Solar + Battery | 290 MW | 2021 | 2028 |
| Sienna 3 2268 | Solar + Battery | 288 MW | 2023 | 2031 |
| TWIN PALMS SOLAR 2048 | Solar + Battery | 288 MW | 2021 | 2030 |
| Queue 26 26 | Solar + Battery | 275 MW | 2022 | 2030 |
| REDONDA 2036 | Solar + Battery | 273 MW | 2021 | 2031 |
| Queue GI-2022-162 GI-2022-162 | Solar + Battery | 270 MW | 2022 | 2026 |
| COBALT 1757 | Solar + Battery | 256.4 MW | 2020 | 2027 |
| Bolt 2248 | Solar + Battery | 255.4 MW | 2023 | 2031 |
| PLUOT 1242 | Solar + Battery | 254 MW | 2016 | 2026 |
| POMEGRANATE 1243 | Solar + Battery | 254 MW | 2016 | 2025 |
| Queue 12 12 | Solar + Battery | 250 MW | 2021 | 2028 |
| Queue 3 3 | Solar + Battery | 250 MW | 2020 | 2027 |
| Queue Q89 Q89 | Solar + Battery | 250 MW | 2022 | 2027 |
| CALVADA SPRINGS SOLAR 1798 | Solar + Battery | 250 MW | 2020 | 2027 |
| HAWKINS SOLAR HYBRID 1736 | Solar + Battery | 250 MW | 2020 | 2027 |
| Cantus 2280 | Solar + Battery | 249.5 MW | 2023 | 2031 |
| MINERAL KING SOLAR 2081 | Solar + Battery | 215.4 MW | 2021 | 2029 |
| Quaking Aspen 2343 | Solar + Battery | 209.6 MW | 2023 | 2029 |
| ELYSIAN 1935 | Solar + Battery | 206.1 MW | 2021 | 2029 |
| Solstice C 2253 | Solar + Battery | 204.5 MW | 2023 | 2031 |
| Solstice D 2251 | Solar + Battery | 204.4 MW | 2023 | 2031 |
| LUNA VALLEY SOLAR 1129 | Solar + Battery | 204 MW | 2015 | 2028 |
| Maravillosa 1 2360 | Solar + Battery | 204 MW | 2023 | 2029 |
| WINSTON HYBRID PV AND BESS 1751 | Solar + Battery | 204 MW | 2020 | 2028 |
| CLARKSON 1956 | Solar + Battery | 203.8 MW | 2021 | 2029 |
| LOTUS SOLAR 2 1934 | Solar + Battery | 203.2 MW | 2021 | 2030 |
| ARATINA SOLAR CENTER 1 1204 | Solar + Battery | 200 MW | 2015 | 2026 |
Showing the 100 largest of 196 projects by requested capacity.
Browse California's full interconnection queue. Compare with operating capacity: 867 operating solar plants in California, 104 operating storage plants in California. Nationwide: Solar plants nationwide, Storage plants nationwide.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).