State queue · Delaware
Delaware interconnection queue
16 proposed generation and storage projects — 8 active and 8 suspended — are in Delaware's interconnection queue, primarily in the PJM Interconnection, totaling 874.4 MW of requested capacity. Battery leads with 350 MW.
16
Proposed projects
874.4 MW
Requested capacity
Battery
Largest resource type
2027
Median planned online year
Requested capacity by resource type
Battery 40.0%Solar 29.7%Offshore Wind 29.2%Other 1.1%
Proposed projects by resource type
Also in the queue (too few for a dedicated page): Battery (2), Offshore Wind (2), Other (1).
All proposed projects in Delaware
| Type | ||||
|---|---|---|---|---|
| Maryland Offshore Wind Energy Project (MOWEP)susp. AB1-056 | Offshore Wind | 247.8 MW | 2015 | 2027 |
| Queue AH2-051 AH2-051 | Battery | 200 MW | 2021 | 2025 |
| Queue AH2-077 AH2-077 | Battery | 150 MW | 2022 | 2027 |
| TerraForm Freeman Solar, LLC project AH1-672 | Solar | 75 MW | 2024 | — |
| Freepoint Solar LLC project AG2-447 | Solar | 20 MW | 2025 | 2024 |
| Cedar Creek Solarsusp. AC2-184 | Solar | 20 MW | 2017 | 2027 |
| Cedar Creek Solarsusp. AC2-185 | Solar | 20 MW | 2017 | 2027 |
| Raceway Solar AC2-187 | Solar | 20 MW | 2017 | 2025 |
| Raceway Solar AC2-188 | Solar | 20 MW | 2017 | 2025 |
| Cedar Creek Solarsusp. AC1-091 | Solar | 19.8 MW | 2016 | 2027 |
| Cedar Creek Solarsusp. AC1-092 | Solar | 19.8 MW | 2016 | 2027 |
| Cedar Creek Solarsusp. AC1-093 | Solar | 18.8 MW | 2016 | 2027 |
| Cedar Creek Solarsusp. AC1-094 | Solar | 15.9 MW | 2016 | 2027 |
| Queue AI2-025 AI2-025 | Other | 10 MW | 2022 | 2026 |
| Raceway Solar AC2-186 | Solar | 10 MW | 2017 | 2025 |
| Maryland Offshore Wind Energy Project (MOWEP)susp. AF1-007 | Offshore Wind | 7.3 MW | 2019 | 2027 |
See 33 operating plants in Delaware · Region: PJM Interconnection.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).