Kansas · Battery

Proposed battery projects in Kansas

There are 31 proposed battery projects in Kansas's interconnection queue, totaling 5.75 GW of requested capacity. The largest is Queue GEN-2020-057 at 424.5 MW, and the median planned online year is 2028.

31
Proposed projects
5.75 GW
Requested capacity
185.3 MW
Average project size
2028
Median planned online year

All proposed battery projects in Kansas

TypeRegionIA Status
Queue GEN-2020-057
GEN-2020-057
BatterySPPFinneyIA Executed424.5 MW20202030
Queue GEN-2021-005
GEN-2021-005
BatterySPPSalineIA Executed350 MW20212030
Queue GEN-2021-006
GEN-2021-006
BatterySPPLabetteFacility Study300 MW20212026
Queue GEN-2024-339
GEN-2024-339
BatterySPPLeavenworthSystem Impact Study300 MW20252029
Queue GEN-2025-SR16
GEN-2025-SR16
BatterySPPSumnerFacility Study300 MW20252026
Queue GEN-2021-029
GEN-2021-029
BatterySPPLinnFacility Study253.8 MW20212026
Queue GEN-2024-176
GEN-2024-176
BatterySPPRenoSystem Impact Study250 MW20252028
Queue GEN-2024-330
GEN-2024-330
BatterySPPButlerSystem Impact Study225 MW20252028
Queue GEN-2020-090
GEN-2020-090
BatterySPPBourbonFacility Study204.3 MW20202026
Queue GEN-2017-227
GEN-2017-227
BatterySPPSedgwickIA Executed201.6 MW20172030
Queue GEN-2022-024
GEN-2022-024
BatterySPPBourbonFacility Study200 MW20222028
Queue GEN-2023-037
GEN-2023-037
BatterySPPWyandotteFacility Study200 MW20232028
Queue GEN-2024-061
GEN-2024-061
BatterySPPCowleySystem Impact Study200 MW20242028
Queue GEN-2024-121
GEN-2024-121
BatterySPPLeavenworthSystem Impact Study199 MW20252028
Queue GEN-2024-189
GEN-2024-189
BatterySPPFordSystem Impact Study199 MW20252028
Queue GEN-2024-319
GEN-2024-319
BatterySPPWyandotteSystem Impact Study199 MW20252028
Queue GEN-2024-320
GEN-2024-320
BatterySPPWyandotteSystem Impact Study199 MW20252028
Queue ERAS-2025-029
ERAS-2025-029
BatterySPPWyandotteIn Progress (unknown study)170 MW20252027
Queue GEN-2017-221
GEN-2017-221
BatterySPPSedgwickIA Executed152 MW20172026
Queue GEN-2021-103
GEN-2021-103
BatterySPPJohnsonIA Executed150 MW20212030
Queue GEN-2024-276
GEN-2024-276
BatterySPPShawneeSystem Impact Study150 MW20252030
Queue GEN-2024-277
GEN-2024-277
BatterySPPShawneeSystem Impact Study150 MW20252030
Queue GEN-2025-SR3
GEN-2025-SR3
BatterySPPClarkIA Pending150 MW20252028
Queue GEN-2025-SR4
GEN-2025-SR4
BatterySPPEdwardsFacility Study150 MW20252028
Queue GEN-2017-196
GEN-2017-196
BatterySPPJohnsonIA Executed128 MW20172030
Queue GEN-2018-108
GEN-2018-108
BatterySPPBarberIA Executed95 MW20182028
Queue GEN-2024-322
GEN-2024-322
BatterySPPGrahamSystem Impact Study75 MW20252029
Queue GEN-2019-053
GEN-2019-053
BatterySPPEdwardsIA Executed50 MW20192028
Queue GEN-2019-063
GEN-2019-063
BatterySPPFordIA Executed50 MW20192028
Queue GEN-2019-068susp.
GEN-2019-068
BatterySPPBartonSuspended50 MW20192029
Queue GEN-2016-160
GEN-2016-160
BatterySPPEllisIA Executed20 MW20162026

Browse Kansas's full interconnection queue. Nationwide: Storage plants nationwide.

Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).