Kentucky · Battery
Proposed battery projects in Kentucky
There are 8 proposed battery projects in Kentucky's interconnection queue, totaling 1.52 GW of requested capacity. The largest is Queue LGE-CS2025-001 at 400 MW, and the median planned online year is 2029.
8
Proposed projects
1.52 GW
Requested capacity
190 MW
Average project size
2029
Median planned online year
All proposed battery projects in Kentucky
| Type | ||||
|---|---|---|---|---|
| Queue LGE-CS2025-001 LGE-CS2025-001 | Battery | 400 MW | 2025 | 2029 |
| Queue 25RSC-005 25RSC-005 | Battery | 250 MW | 2025 | 2030 |
| Queue J2844 J2844 | Battery | 200 MW | 2022 | 2025 |
| Queue 25RSC-004 25RSC-004 | Battery | 200 MW | 2025 | 2030 |
| Queue LGE-CS2025-003 LGE-CS2025-003 | Battery | 125 MW | 2025 | 2029 |
| Queue LGE-GIS-2023-003 LGE-GIS-2023-003 | Battery | 125 MW | 2023 | 2026 |
| Queue LGE-GIS-2021-013 LGE-GIS-2021-013 | Battery | 120 MW | 2021 | 2028 |
| Threeforks Energy Storage AF1-162 | Battery | 100 MW | 2019 | 2028 |
Browse Kentucky's full interconnection queue. Nationwide: Storage plants nationwide.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition). Data: LBNL backbone through December 31, 2025; ISO-region statuses refreshed monthly (last: July 2026); non-ISO West and Southeast as of the LBNL edition.