Proposed battery projects in Kentucky

There are 8 proposed battery projects in Kentucky's interconnection queue, totaling 1.52 GW of requested capacity. The largest is Queue LGE-CS2025-001 at 400 MW, and the median planned online year is 2029.

8
Proposed projects
1.52 GW
Requested capacity
190 MW
Average project size
2029
Median planned online year

All proposed battery projects in Kentucky

TypeRegionIA Status
Queue LGE-CS2025-001
LGE-CS2025-001
BatterySoutheastJeffersonIn Progress (unknown study)400 MW20252029
Queue 25RSC-005
25RSC-005
BatterySoutheastMccrackenIn Progress (unknown study)250 MW20252030
Queue J2844
J2844
BatteryMISOHendersonCluster Study200 MW20222025
Queue 25RSC-004
25RSC-004
BatterySoutheastMarshallIn Progress (unknown study)200 MW20252030
Queue LGE-CS2025-003
LGE-CS2025-003
BatterySoutheastCrittendenIn Progress (unknown study)125 MW20252029
Queue LGE-GIS-2023-003
LGE-GIS-2023-003
BatterySoutheastMercerIn Progress (unknown study)125 MW20232026
Queue LGE-GIS-2021-013
LGE-GIS-2021-013
BatterySoutheastHardinIA Executed120 MW20212028
Threeforks Energy Storage
AF1-162
BatteryPJMMartinIA Executed100 MW20192028