State queue · Kentucky

Kentucky interconnection queue

134 proposed generation and storage projects — 126 active and 8 suspended — are in Kentucky's interconnection queue, primarily in the Non-ISO Southeast, totaling 21.50 GW of requested capacity. Solar leads with 8.81 GW.

134
Proposed projects
21.50 GW
Requested capacity
Solar
Largest resource type
2026
Median planned online year

Requested capacity by resource type

Solar 41.0%Gas 39.1%Solar + Battery 8.5%Battery 8.0%Coal 1.6%Wind 0.9%Other 0.7%Hydro 0.2%

Proposed projects by resource type

Also in the queue (too few for a dedicated page): Coal (2), Wind (1), Other (1), Hydro (3).

All proposed projects in Kentucky

TypeRegion
Queue 628
628
GasSoutheastTodd1.60 GW20242030
Queue AH2-351
AH2-351
SolarPJM1.00 GW20222027
Queue AH2-353
AH2-353
SolarPJM1.00 GW20222028
East Kentucky Power Cooperative, Inc. project
AH1-721
GasPJM786 MW2025
Queue LGE-GIS-2009-004
LGE-GIS-2009-004
GasSoutheastTrimble785 MW20092010
Queue 417
417
GasSoutheastMuhlenberg780 MW20202022
Queue LGE-GIS-2013-001
LGE-GIS-2013-001
GasSoutheastJefferson691 MW20132015
Queue LGE-GIS-2010-001
LGE-GIS-2010-001
GasSoutheastJefferson690 MW20102015
Queue LGE-CS2025-002
LGE-CS2025-002
GasSoutheastJefferson680 MW20252031
Queue LGE-GIS-2022-003
LGE-GIS-2022-003
GasSoutheastJefferson660 MW20222027
Queue LGE-GIS-2023-002
LGE-GIS-2023-002
GasSoutheastMercer660 MW20232030
Queue LGE-CS2025-001
LGE-CS2025-001
BatterySoutheastJefferson400 MW20252029
Queue J2931
J2931
SolarMISOHenderson400 MW20222025
Queue J1466
J1466
SolarMISOHenderson250 MW20192025
Queue 25RSC-005
25RSC-005
BatterySoutheastMccracken250 MW20252030
Queue 536
536
SolarSoutheastMuhlenberg250 MW20232026
Goldfinch Solar
AF2-111
SolarPJMMason250 MW20202030
STMO bn, LLC project
AG2-184
SolarPJMKnott210 MW20252024
Queue LGE-CS2025-004
LGE-CS2025-004
Solar + BatterySoutheastLincoln200 MW20252029
Queue LGE-GIS-2021-009susp.
LGE-GIS-2021-009
Solar + BatterySoutheastHardin200 MW20212026
Queue J2844
J2844
BatteryMISOHenderson200 MW20222025
Queue J2930
J2930
WindMISOHenderson200 MW20222025
Queue J762
J762
SolarMISOMeade200 MW20162021
STMO bn, LLC project
AH1-617
SolarPJM200 MW20252024
Queue 25RSC-004
25RSC-004
BatterySoutheastMarshall200 MW20252030
Lynn Bark Energy Center
AF2-018
SolarPJMMartin200 MW20192029
Martin County Solar Projectsusp.
AF1-130
SolarPJMMartin190 MW20192028
Fleming Solar
AF1-233
SolarPJMFleming188.5 MW20192029
Queue G002
G002
CoalMISOTrimble174 MW19982016
Queue G003
G003
CoalMISOTrimble174 MW19982004
Queue G016
G016
GasMISOTrimble174 MW19992005
Queue G017
G017
GasMISOTrimble174 MW19992004
Queue G018
G018
GasMISOTrimble174 MW19992004
Queue G069
G069
GasMISOTrimble174 MW20002001
Queue 364
364
SolarSoutheastLogan173 MW20192024
Queue J1619
J1619
SolarMISOWebster160 MW20202024
Queue J1450
J1450
SolarMISOWebster150 MW20192025
Queue J1638
J1638
SolarMISOHancock150 MW20222026
Queue J1696
J1696
SolarMISOHenderson150 MW20202026
Queue J2540
J2540
SolarMISOGraves150 MW20252026
Queue AH2-021
AH2-021
Solar + BatteryPJMBarren150 MW20212026
Exie Solar
AG1-354
SolarPJMGreen150 MW20202028
Surplus; J1450
S1073
OtherMISOWebster150 MW20252026
Queue 25RSC-010
25RSC-010
Solar + BatterySoutheastGraves140 MW20252031
Queue LGE-GIS-2023-007
LGE-GIS-2023-007
SolarSoutheastHopkins138 MW20232027
Queue LGE-CS2025-003
LGE-CS2025-003
BatterySoutheastCrittenden125 MW20252029
Queue LGE-GIS-2023-003
LGE-GIS-2023-003
BatterySoutheastMercer125 MW20232026
Queue LGE-GIS-2021-007susp.
LGE-GIS-2021-007
SolarSoutheastMccracken120 MW20212026
Queue LGE-GIS-2021-010
LGE-GIS-2021-010
SolarSoutheastMarion120 MW20212026
Queue LGE-GIS-2021-013
LGE-GIS-2021-013
BatterySoutheastHardin120 MW20212028
Queue LGE-GIS-2021-020
LGE-GIS-2021-020
Solar + BatterySoutheastMccracken120 MW20212026
Queue 649
649
SolarSoutheastMuhlenberg119 MW20242033
Queue LGE-GIS-2021-018susp.
LGE-GIS-2021-018
Solar + BatterySoutheastBath110 MW20212027
Summer Shade Solar
AG1-341
Solar + BatteryPJMMetcalfe106 MW20202028
Queue LGE-CS2025-013
LGE-CS2025-013
SolarSoutheastBallard100 MW20252028
Queue LGE-GIS-2021-017susp.
LGE-GIS-2021-017
Solar + BatterySoutheastMason100 MW20212026
Queue LGE-GIS-2021-019susp.
LGE-GIS-2021-019
SolarSoutheastBoyle100 MW20212027
Queue J2739
J2739
SolarMISOOhio100 MW20222026
Queue J3165
J3165
SolarMISOBreckinridge100 MW20222025
Hummingbird Energy LLC project
AH1-664
SolarPJMFleming100 MW2025
Queue AH2-125
AH2-125
BatteryPJM100 MW20222028
Queue AI1-180
AI1-180
Solar + BatteryPJM100 MW20222027
Madison Solar 1
AE2-308
SolarPJMMadison100 MW20192021
Surplus; J1638
S1083
BatteryMISOHancock100 MW20252029
Threeforks Energy Storage
AF1-162
BatteryPJMMartin100 MW20192028
Queue LGE-GIS-2019-025
LGE-GIS-2019-025
SolarSoutheastMercer99 MW20192026
Queue 609
609
SolarSoutheastMccracken96 MW20242027
Queue 642
642
SolarSoutheastMuhlenberg96 MW20242033
Northern Bobwhite Solar
AE1-143
SolarPJMMarion96 MW20182027
Queue LGE-GIS-2024-006
LGE-GIS-2024-006
GasSoutheastJefferson94 MW20242026
Queue LGE-GIS-2017-002
LGE-GIS-2017-002
SolarSoutheastLyon86 MW20172024
Queue AH2-130
AH2-130
SolarPJM85 MW20222026
Queue AI1-165
AI1-165
Solar + BatteryPJMGreen85 MW20222026
Queue AI1-132
AI1-132
Solar + BatteryPJMWashington83 MW20222029
Stonecrop Solar
AG1-320
SolarPJMHardin82 MW20202029
Clinton Solar, LLC project
AH1-239
SolarPJMBoone80 MW20252024
Hummingbird Energy LLC project
AH1-665
SolarPJMFleming80 MW2025
Fleming Solar, LLC project
AH1-666
SolarPJMFleming80 MW2025
Queue AH2-002
AH2-002
SolarPJMBarren80 MW20212024
Bright Mountain Solar
AG1-066
SolarPJMPerry80 MW20202027
Queue LGE-GIS-2024-002
LGE-GIS-2024-002
GasSoutheastHopkins75 MW20242027
Queue 650
650
SolarSoutheastMuhlenberg72 MW20242029
Queue AH2-383
AH2-383
Solar + BatteryPJMFleming70 MW20222027
Blue Moon Solar
AD2-048
SolarPJMHarrison70 MW20182026
Queue 388
388
SolarSoutheastSimpson69 MW20192025
Queue AI1-079
AI1-079
Solar + BatteryPJMAdair64.8 MW20222026
Magnolia Solar and Grazing Farm LLC project
AG2-424
Solar + BatteryPJMLarue63.2 MW20252023
Queue J1649
J1649
SolarMISOMccracken60 MW20212025
Queue 657
657
GasSoutheastMuhlenberg60 MW20242030
Horseshoe Bend Solar
AF1-050
SolarPJMGreen60 MW20192026
Mt Olive Creek Solar
AF1-038
SolarPJMRussell60 MW20192026
Flat Run Solar
AF1-083
SolarPJMBarren55 MW20192026
Barrelhead
AG1-471
SolarPJM54 MW20202029
SR Madison, LLC project
AG2-073
SolarPJMMadison53 MW20252024
Queue AH2-076
AH2-076
Solar + BatteryPJMPerry52.5 MW20222023
Queue J1604
J1604
SolarMISOHenderson50 MW20202026
Queue J2541
J2541
SolarMISOGraves50 MW20252026
Queue AI1-019
AI1-019
Solar + BatteryPJM50 MW20222026
Queue AI1-133
AI1-133
Solar + BatteryPJMFleming50 MW20222029
Pike County Solarsusp.
AC1-101
SolarPJMPike50 MW20162028

Showing the 100 largest of 134 projects by requested capacity.

See 58 operating plants in Kentucky · Regions: Non-ISO Southeast, PJM Interconnection, MISO.

Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).