Michigan · Gas

Proposed gas projects in Michigan

There are 14 proposed gas projects in Michigan's interconnection queue, totaling 9.74 GW of requested capacity. The largest is Queue J4024 at 1.50 GW, and the median planned online year is 2027.

14
Proposed projects
9.74 GW
Requested capacity
695.8 MW
Average project size
2027
Median planned online year

All proposed gas projects in Michigan

TypeRegionIA Status
Queue J4024
J4024
GasMISOMonroe1.50 GW20252030
Queue J4025
J4025
GasMISOMonroe1.50 GW20252030
Queue J3799
J3799
GasMISOLivingston1.45 GW20242030
Queue J3922
J3922
GasMISOBranch1.45 GW20252030
Queue J3923
J3923
GasMISOWashtenaw1.41 GW20252030
Queue J3935
J3935
GasMISOGenesee1.27 GW20252030
Queue J4159
J4159
GasMISOOttawa664 MW20252028
Queue J4160
J4160
GasMISOOttawa425 MW20252026
Queue J1262
J1262
GasMISOWayneIA Executed25 MW20192022
Queue J1798
J1798
GasMISOWayneIA Executed25 MW20202023
Queue J2969
J2969
GasMISOKalkaskaCluster Study13.4 MW20222002
Queue J571
J571
GasMISOKalamazooIA Executed6.4 MW20162018
Queue J3756
J3756
GasMISOMarquetteIn Progress (unknown study)4.2 MW20242019
Queue J3800
J3800
GasMISOBaragaIn Progress (unknown study)1.8 MW20242019

Browse Michigan's full interconnection queue. Compare with operating capacity: 61 operating natural gas plants in Michigan. Nationwide: Natural Gas plants nationwide.

Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).