State queue · Michigan
Michigan interconnection queue
302 proposed generation and storage projects — 301 active and 1 suspended — are in Michigan's interconnection queue, primarily in the MISO, totaling 58.64 GW of requested capacity. Solar leads with 22.80 GW.
302
Proposed projects
58.64 GW
Requested capacity
Solar
Largest resource type
2026
Median planned online year
Requested capacity by resource type
Solar 38.9%Battery 25.1%Gas 16.6%Wind 10.6%Solar + Battery 4.3%Other 3.3%Nuclear 1.3%
Proposed projects by resource type
Solar projects147 · 22.80 GWBattery projects85 · 14.73 GWGas projects14 · 9.74 GWWind projects30 · 6.21 GWSolar + Battery projects13 · 2.51 GW
Also in the queue (too few for a dedicated page): Other (12), Nuclear (1).
All proposed projects in Michigan
| Type | ||||
|---|---|---|---|---|
| Queue J4024 J4024 | Gas | 1.50 GW | 2025 | 2030 |
| Queue J4025 J4025 | Gas | 1.50 GW | 2025 | 2030 |
| Queue J3799 J3799 | Gas | 1.45 GW | 2024 | 2030 |
| Queue J3922 J3922 | Gas | 1.45 GW | 2025 | 2030 |
| Queue J3923 J3923 | Gas | 1.41 GW | 2025 | 2030 |
| Queue J3935 J3935 | Gas | 1.27 GW | 2025 | 2030 |
| Replacing 749 MW of coal generation with BESS; Campbell 3 R1040 | Other | 749 MW | 2023 | 2028 |
| Queue J4040 J4040 | Nuclear | 735 MW | 2025 | 2030 |
| Queue J4159 J4159 | Gas | 664 MW | 2025 | 2028 |
| Queue J4102 J4102 | Solar | 539 MW | 2025 | 2029 |
| Queue J2590 J2590 | Battery | 500 MW | 2022 | 2025 |
| Queue J1586 J1586 | Solar + Battery | 499 MW | 2020 | 2025 |
| Queue J3966 J3966 | Wind | 480 MW | 2025 | 2029 |
| Monroe ERAS E0018 | Battery | 432 MW | 2025 | 2028 |
| Queue J4160 J4160 | Gas | 425 MW | 2025 | 2026 |
| Queue J3992 J3992 | Battery | 400 MW | 2025 | 2028 |
| Queue J4093 J4093 | Battery | 400 MW | 2025 | 2030 |
| Queue J3994 J3994 | Battery | 360 MW | 2025 | 2028 |
| Queue J3872 J3872 | Battery | 350 MW | 2025 | 2029 |
| Queue J4203 J4203 | Wind | 350 MW | 2025 | 2028 |
| Queue J2098 J2098 | Solar | 309 MW | 2021 | 2026 |
| Queue J3723 J3723 | Solar | 300 MW | 2024 | 2028 |
| Queue J3843 J3843 | Solar | 300 MW | 2024 | 2027 |
| Queue J3866 J3866 | Wind | 300 MW | 2024 | 2028 |
| Queue J3887 J3887 | Wind | 300 MW | 2025 | 2030 |
| Queue J4016 J4016 | Battery | 300 MW | 2025 | 2029 |
| Queue J4094 J4094 | Battery | 300 MW | 2025 | 2030 |
| Queue J4095 J4095 | Battery | 300 MW | 2025 | 2030 |
| Queue J4195 J4195 | Wind | 300 MW | 2025 | 2030 |
| Three Lakes Solar AF1-176 | Solar + Battery | 300 MW | 2019 | 2022 |
| Queue J3282 J3282 | Solar | 297 MW | 2024 | 2028 |
| Queue J1557 J1557 | Wind | 293 MW | 2020 | 2026 |
| Queue J3274 J3274 | Solar | 290 MW | 2024 | 2028 |
| Queue J3313 J3313 | Wind | 263 MW | 2024 | 2028 |
| Queue J3050 J3050 | Solar | 255 MW | 2025 | 2027 |
| Queue J3971 J3971 | Wind | 255 MW | 2025 | 2029 |
| Queue J3361 J3361 | Wind | 254 MW | 2024 | 2027 |
| Queue J2260 J2260 | Wind | 251.5 MW | 2021 | 2023 |
| Queue J1614 J1614 | Solar | 250 MW | 2020 | 2025 |
| Queue J2100 J2100 | Battery | 250 MW | 2021 | 2024 |
| Queue J2139 J2139 | Solar + Battery | 250 MW | 2021 | 2024 |
| Queue J2628 J2628 | Battery | 250 MW | 2022 | 2028 |
| Queue J2921 J2921 | Solar | 250 MW | 2022 | 2026 |
| Queue J3438 J3438 | Battery | 250 MW | 2024 | 2028 |
| Queue J3656 J3656 | Battery | 250 MW | 2024 | 2028 |
| Queue J3836 J3836 | Battery | 250 MW | 2024 | 2028 |
| Queue J3845 J3845 | Battery | 250 MW | 2024 | 2029 |
| Queue J3865 J3865 | Wind | 250 MW | 2024 | 2028 |
| Queue J3977 J3977 | Battery | 250 MW | 2025 | 2029 |
| Queue J4026 J4026 | Battery | 250 MW | 2025 | 2029 |
| Queue J4058 J4058 | Battery | 250 MW | 2025 | 2028 |
| Queue J4066 J4066 | Solar | 250 MW | 2025 | 2030 |
| Queue J4167 J4167 | Battery | 250 MW | 2025 | 2030 |
| FERMI Storage Project E0008 | Battery | 248 MW | 2025 | 2028 |
| Queue J3945 J3945 | Solar | 245 MW | 2025 | 2030 |
| Queue J2567 J2567 | Battery | 240 MW | 2022 | 2025 |
| Queue J3864 J3864 | Wind | 230 MW | 2024 | 2028 |
| Queue J2668 J2668 | Solar | 225 MW | 2022 | 2025 |
| Queue J2673 J2673 | Solar | 225 MW | 2022 | 2025 |
| Queue J3696 J3696 | Battery | 225 MW | 2024 | 2026 |
| Queue J3838 J3838 | Solar | 225 MW | 2024 | 2028 |
| Queue J2670 J2670 | Solar | 223 MW | 2022 | 2025 |
| Queue J2001 J2001 | Solar | 220 MW | 2021 | 2025 |
| Queue J2444 J2444 | Solar | 220 MW | 2022 | 2026 |
| Queue J2814 J2814 | Solar | 220 MW | 2022 | 2026 |
| Queue J3496 J3496 | Wind | 220 MW | 2024 | 2027 |
| Queue J3646 J3646 | Battery | 220 MW | 2024 | 2028 |
| Replacing 220 MW of coal generation with BESS; Trenton Channel 9 R1041 | Other | 220 MW | 2023 | 2025 |
| Queue J2611 J2611 | Solar | 215 MW | 2022 | 2028 |
| Queue J3940 J3940 | Solar | 214 MW | 2025 | 2030 |
| Deckerville Solar Park Project E0019 | Solar | 213.2 MW | 2025 | 2028 |
| Queue J1062 J1062 | Solar | 200 MW | 2018 | 2023 |
| Queue J1196 J1196 | Solar | 200 MW | 2019 | 2025 |
| Queue J1226 J1226 | Solar | 200 MW | 2019 | 2024 |
| Queue J1255 J1255 | Solar | 200 MW | 2019 | 2025 |
| Queue J1379 J1379 | Solar | 200 MW | 2019 | 2025 |
| Queue J1525 J1525 | Solar | 200 MW | 2020 | 2026 |
| Queue J1550 J1550 | Solar | 200 MW | 2020 | 2025 |
| Queue J1571 J1571 | Solar | 200 MW | 2021 | 2025 |
| Queue J1603 J1603 | Solar | 200 MW | 2021 | 2025 |
| Queue J1663 J1663 | Solar | 200 MW | 2021 | 2025 |
| Queue J1664 J1664 | Solar | 200 MW | 2020 | 2026 |
| Queue J1894 J1894 | Battery | 200 MW | 2021 | 2024 |
| Queue J1900 J1900 | Battery | 200 MW | 2021 | 2024 |
| Queue J1902 J1902 | Battery | 200 MW | 2021 | 2024 |
| Queue J2061 J2061 | Solar | 200 MW | 2021 | 2024 |
| Queue J2374 J2374 | Solar | 200 MW | 2022 | 2025 |
| Queue J2475 J2475 | Battery | 200 MW | 2022 | 2026 |
| Queue J2485 J2485 | Solar | 200 MW | 2022 | 2025 |
| Queue J2486 J2486 | Solar | 200 MW | 2022 | 2025 |
| Queue J2667 J2667 | Solar | 200 MW | 2022 | 2025 |
| Queue J2672 J2672 | Solar | 200 MW | 2022 | 2025 |
| Queue J2676 J2676 | Solar | 200 MW | 2022 | 2025 |
| Queue J2677 J2677 | Solar | 200 MW | 2022 | 2025 |
| Queue J2684 J2684 | Battery | 200 MW | 2022 | 2025 |
| Queue J2799 J2799 | Battery | 200 MW | 2025 | 2025 |
| Queue J2822 J2822 | Battery | 200 MW | 2022 | 2025 |
| Queue J2877 J2877 | Solar | 200 MW | 2022 | 2025 |
| Queue J2878 J2878 | Solar | 200 MW | 2022 | 2025 |
| Queue J2889 J2889 | Battery | 200 MW | 2022 | 2025 |
Showing the 100 largest of 302 projects by requested capacity.
See 272 operating plants in Michigan · Regions: MISO, PJM Interconnection.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).