Michigan · Solar

Proposed solar projects in Michigan

There are 147 proposed solar projects in Michigan's interconnection queue, totaling 22.80 GW of requested capacity. The largest is Queue J4102 at 539 MW, and the median planned online year is 2025.

147
Proposed projects
22.80 GW
Requested capacity
155.1 MW
Average project size
2025
Median planned online year

All proposed solar projects in Michigan

TypeRegionIA Status
Queue J4102
J4102
SolarMISOCass539 MW20252029
Queue J2098
J2098
SolarMISOCalhounCluster Study309 MW20212026
Queue J3723
J3723
SolarMISOWexfordIn Progress (unknown study)300 MW20242028
Queue J3843
J3843
SolarMISOSaginaw300 MW20242027
Queue J3282
J3282
SolarMISOMasonIn Progress (unknown study)297 MW20242028
Queue J3274
J3274
SolarMISOOgemawIn Progress (unknown study)290 MW20242028
Queue J3050
J3050
SolarMISOCalhounCluster Study255 MW20252027
Queue J1614
J1614
SolarMISOMuskegonIA Executed250 MW20202025
Queue J2921
J2921
SolarMISOCalhounCluster Study250 MW20222026
Queue J4066
J4066
SolarMISOIsabella250 MW20252030
Queue J3945
J3945
SolarMISOWashtenaw245 MW20252030
Queue J2668
J2668
SolarMISOMasonCluster Study225 MW20222025
Queue J2673
J2673
SolarMISOClareCluster Study225 MW20222025
Queue J3838
J3838
SolarMISOIngham225 MW20242028
Queue J2670
J2670
SolarMISOMasonCluster Study223 MW20222025
Queue J2001
J2001
SolarMISONewaygoCluster Study220 MW20212025
Queue J2444
J2444
SolarMISOVan BurenCluster Study220 MW20222026
Queue J2814
J2814
SolarMISOKalamazooCluster Study220 MW20222026
Queue J2611
J2611
SolarMISOAlconaCluster Study215 MW20222028
Queue J3940
J3940
SolarMISOIsabella214 MW20252030
Deckerville Solar Park Project
E0019
SolarMISOSanilacIn Progress (unknown study)213.2 MW20252028
Queue J1062
J1062
SolarMISOWashtenawIA Executed200 MW20182023
Queue J1196
J1196
SolarMISOSanilacIA Executed200 MW20192025
Queue J1226
J1226
SolarMISOLenaweeConstruction200 MW20192024
Queue J1255
J1255
SolarMISOIoniaConstruction200 MW20192025
Queue J1379
J1379
SolarMISOMontcalmIA Executed200 MW20192025
Queue J1525
J1525
SolarMISOHuronIA Executed200 MW20202026
Queue J1550
J1550
SolarMISOBranchIA Executed200 MW20202025
Queue J1571
J1571
SolarMISOLenaweeIA Executed200 MW20212025
Queue J1603
J1603
SolarMISOOtsegoIA Executed200 MW20212025
Queue J1663
J1663
SolarMISOOttawaConstruction200 MW20212025
Queue J1664
J1664
SolarMISOSt. ClairIA Executed200 MW20202026
Queue J2061
J2061
SolarMISOSaginawCluster Study200 MW20212024
Queue J2374
J2374
SolarMISOSanilacCluster Study200 MW20222025
Queue J2485
J2485
SolarMISOLivingstonCluster Study200 MW20222025
Queue J2486
J2486
SolarMISOMonroeCluster Study200 MW20222025
Queue J2667
J2667
SolarMISOSanilacCluster Study200 MW20222025
Queue J2672
J2672
SolarMISOShiawasseeCluster Study200 MW20222025
Queue J2676
J2676
SolarMISOHuronCluster Study200 MW20222025
Queue J2677
J2677
SolarMISOSt. ClairCluster Study200 MW20222025
Queue J2877
J2877
SolarMISOMidlandCluster Study200 MW20222025
Queue J2878
J2878
SolarMISOSanilacCluster Study200 MW20222025
Queue J3286
J3286
SolarMISOSanilacIn Progress (unknown study)200 MW20242028
Queue J3287
J3287
SolarMISOOsceolaIn Progress (unknown study)200 MW20242028
Queue J3472
J3472
SolarMISOLapeerIn Progress (unknown study)200 MW20242028
Queue J3545
J3545
SolarMISOIoniaIn Progress (unknown study)200 MW20242028
Queue J3633
J3633
SolarMISOSanilacIn Progress (unknown study)200 MW20242028
Queue J3803
J3803
SolarMISOMonroeIn Progress (unknown study)200 MW20242028
Queue J3837
J3837
SolarMISOVan Buren200 MW20242029
Queue J3852
J3852
SolarMISOTuscola200 MW20242030
Queue J3859
J3859
SolarMISOBranch200 MW20242028
Queue J3908
J3908
SolarMISOSt. Joseph196 MW20252025
Queue J4044
J4044
SolarMISOLenawee190 MW20252028
Queue J799
J799
SolarMISOWashtenawConstruction189 MW20172021
Queue J1944
J1944
SolarMISOSanilacCluster Study185 MW20212023
Bankson Solar Project, LLC project
AH1-272
SolarPJMVan BurenSystem Impact Study185 MW20252025
Queue J1658
J1658
SolarMISOHillsdaleIA Executed180 MW20252025
Queue J2578
J2578
SolarMISOTuscolaCluster Study180 MW20222026
Au Gres Solar Project
E0007
SolarMISOArenacIn Progress (unknown study)179.5 MW20252028
Queue J4043
J4043
SolarMISOEaton178 MW20252028
Queue J2876
J2876
SolarMISOArenacCluster Study175 MW20222025
Queue J3059
J3059
SolarMISOMidlandCluster Study175 MW20222026
Queue J1224
J1224
SolarMISOWashtenawConstruction170 MW20192025
Queue J1297
J1297
SolarMISOShiawasseeConstruction170 MW20192024
Queue J2675
J2675
SolarMISOGladwinCluster Study170 MW20222025
Queue J1917
J1917
SolarMISOLivingstonCluster Study165 MW20212023
Queue J3827
J3827
SolarMISOMackinac160 MW20242028
Queue J4047
J4047
SolarMISOTuscola160 MW20252028
Queue J1320
J1320
SolarMISOBranchIA Executed150 MW20192025
Queue J1553
J1553
SolarMISOClintonIA Executed150 MW20212025
Queue J1914
J1914
SolarMISOPresque IsleCluster Study150 MW20232026
Queue J2678
J2678
SolarMISODeltaCluster Study150 MW20222025
Queue J2875
J2875
SolarMISOPresque IsleCluster Study150 MW20222025
Queue J3134
J3134
SolarMISOOtsegoCluster Study150 MW20222025
Queue J3419
J3419
SolarMISOHuronIn Progress (unknown study)150 MW20242028
Queue J3471
J3471
SolarMISOBranchIn Progress (unknown study)150 MW20242028
Queue J3473
J3473
SolarMISOBayIn Progress (unknown study)150 MW20242028
Queue J3644
J3644
SolarMISOBayIn Progress (unknown study)150 MW20242028
Queue J3682
J3682
SolarMISOMuskegonIn Progress (unknown study)150 MW20242028
Queue J3722
J3722
SolarMISOHillsdaleIn Progress (unknown study)150 MW20242028
Queue J3844
J3844
SolarMISOSt. Joseph150 MW20242029
Queue J4061
J4061
SolarMISOLenawee150 MW20252028
Queue J875
J875
SolarMISOLenaweeConstruction150 MW20172022
Gemstone Solar
AF2-083
SolarPJMCassIA Executed150 MW20202028
Wingstem Solar Energy Farmsusp.
AE1-170
SolarPJMCassIA Executed150 MW20182025
Queue J1750
J1750
SolarMISOMarquetteConstruction149.7 MW20222026
Queue J3761
J3761
SolarMISOOgemawIn Progress (unknown study)145.8 MW20242027
Queue J2669
J2669
SolarMISOMasonCluster Study140 MW20222025
Queue J2812
J2812
SolarMISOHillsdaleCluster Study140 MW20222026
Queue J2815
J2815
SolarMISOCalhounCluster Study140 MW20222026
Queue J3283
J3283
SolarMISOGrand TraverseIn Progress (unknown study)135 MW20242028
Queue J1918
J1918
SolarMISOMontcalmCluster Study132 MW20212026
Queue J3835
J3835
SolarMISOSaginaw130 MW20242028
Queue J1203
J1203
SolarMISOGeneseeConstruction125 MW20192025
Queue J1310
J1310
SolarMISOJacksonConstruction125 MW20192024
Queue J1939
J1939
SolarMISOSaginawCluster Study125 MW20232023
Queue J2490
J2490
SolarMISOTuscolaCluster Study125 MW20222025
Queue J3792
J3792
SolarMISOGratiotIn Progress (unknown study)125 MW20242028
Queue J857
J857
SolarMISOCalhounConstruction125 MW20172022
Queue J1389
J1389
SolarMISOSaginawIA Executed120 MW20192025

Showing the 100 largest of 147 projects by requested capacity.

Browse Michigan's full interconnection queue. Compare with operating capacity: 61 operating solar plants in Michigan. Nationwide: Solar plants nationwide.

Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).