State queue · Mississippi

Mississippi interconnection queue

93 proposed generation and storage projects — 88 active and 5 suspended — are in Mississippi's interconnection queue, primarily in the MISO, totaling 17.04 GW of requested capacity. Solar leads with 8.43 GW.

93
Proposed projects
17.04 GW
Requested capacity
Solar
Largest resource type
2027
Median planned online year

Requested capacity by resource type

Solar 49.5%Gas 19.6%Solar + Battery 14.1%Battery 11.3%Wind 5.6%

Proposed projects by resource type

All proposed projects in Mississippi

TypeRegion
Queue J1813
J1813
GasMISODesoto1.00 GW20222002
Lakeover CCCT
E0047
GasMISOHinds820 MW20252028
Vicksburg CCCT
E0031
GasMISOWarren820 MW20252027
Queue 569
569
GasSoutheastLowndes620 MW20232026
Queue J2966
J2966
SolarMISOQuitman450 MW20222025
Queue J2173
J2173
Solar + BatteryMISOHinds396 MW20212027
Queue J1946
J1946
Solar + BatteryMISOJasper350 MW20212024
Queue J3623
J3623
WindMISOSunflower350 MW20242028
Queue J4121
J4121
SolarMISOWashington300 MW20252030
Queue J2091
J2091
BatteryMISODesoto250 MW20222025
Queue J2602
J2602
SolarMISODesoto250 MW20222026
Queue J2999
J2999
SolarMISOPerry250 MW20222025
Queue IC-986susp.
IC-986
SolarSoutheastLamar250 MW20212025
Queue J3139
J3139
SolarMISOHolmes225 MW20222026
Queue J1458
J1458
SolarMISOWashington200 MW20192024
Queue J1891
J1891
Solar + BatteryMISOAttala200 MW20212027
Queue J2289
J2289
SolarMISOSunflower200 MW20212028
Queue J2330
J2330
SolarMISOLeflore200 MW20222026
Queue J2893
J2893
Solar + BatteryMISOHolmes200 MW20222027
Queue J4073
J4073
SolarMISOCoahoma200 MW20252029
Queue J4119
J4119
BatteryMISORankin200 MW20252029
Queue J4154
J4154
BatteryMISOMadison200 MW20252028
Queue J4189
J4189
SolarMISOSunflower200 MW20252030
Queue J866
J866
WindMISOTunica200 MW20172021
Queue IC-1113susp.
IC-1113
SolarSoutheastLamar200 MW20232027
Queue IC-1180susp.
IC-1180
SolarSoutheastJones200 MW20232028
Queue 25RSC-013
25RSC-013
BatterySoutheastLowndes200 MW20252031
Queue 423
423
SolarSoutheastClay200 MW20202026
Queue 429
429
BatterySoutheastClay200 MW20202028
Queue 466
466
SolarSoutheastClay200 MW20212028
Queue 512
512
SolarSoutheastLee200 MW20222028
Queue 600
600
BatterySoutheastClay200 MW20232026
Queue J2047
J2047
SolarMISODesoto199 MW20212024
Queue J3049
J3049
SolarMISOMadison188 MW20222024
Queue J2571
J2571
WindMISOTunica176.6 MW20222024
Queue J2127
J2127
Solar + BatteryMISOJefferson Davis172.5 MW20212027
Queue J3764
J3764
Solar + BatteryMISOMadison170 MW20242028
Queue S1127
S1127
BatteryMISOWashington170 MW20252027
Queue IC-1146susp.
IC-1146
SolarSoutheastStone170 MW20232029
Queue J3053
J3053
SolarMISOMadison169 MW20222024
Queue J2873
J2873
SolarMISOSimpson165 MW20222027
Queue J3987
J3987
SolarMISOAmite165 MW20242030
Queue 25-IC-1355
25-IC-1355
SolarSoutheastJasper165 MW20252029
Queue J3900
J3900
WindMISOSunflower163 MW20242030
Queue J1440
J1440
SolarMISOTunica160 MW20192024
Queue J3175
J3175
SolarMISOTunica160 MW20222026
Queue IC-1145
IC-1145
SolarSoutheastJasper156 MW20232028
Queue J1672
J1672
SolarMISOHinds150 MW20202025
Queue J2720
J2720
SolarMISOYazoo150 MW20222025
Queue J2740
J2740
SolarMISOSunflower150 MW20222029
Queue J2869
J2869
Solar + BatteryMISOSunflower150 MW20222027
Queue J4083
J4083
BatteryMISOPerry150 MW20252030
Queue 425
425
SolarSoutheastChickasaw150 MW20202027
Queue 422
422
SolarSoutheastChickasaw145 MW20202027
Queue J3913
J3913
SolarMISOAmite140 MW20242030
Queue 672
672
SolarSoutheastRankin140 MW20242027
Queue J2287
J2287
SolarMISOBolivar135 MW20212024
Queue J2751
J2751
SolarMISOBolivar125 MW20222026
Queue J2685
J2685
SolarMISOSharkey120 MW20252026
Queue J2752
J2752
SolarMISOMontgomery110 MW20222026
Queue J1748
J1748
SolarMISODesoto100 MW20202025
Queue J2297
J2297
SolarMISOSunflower100 MW20212026
Queue J2761
J2761
SolarMISOMarion100 MW20222029
Queue J2763
J2763
Solar + BatteryMISOSunflower100 MW20222025
Queue J2957
J2957
Solar + BatteryMISOPanola100 MW20222027
Queue J3028
J3028
Solar + BatteryMISOPerry100 MW20222027
Queue J3093
J3093
BatteryMISOMadison100 MW20222024
Queue J3186
J3186
Solar + BatteryMISOBolivar100 MW20222027
Queue J3231
J3231
Solar + BatteryMISOAmite100 MW20222024
Queue J4046
J4046
SolarMISOAttala100 MW20252030
Queue J4131
J4131
BatteryMISOScott100 MW20252030
Queue J604
J604
SolarMISOSunflower100 MW20162021
Queue J908
J908
SolarMISOTallahatchie100 MW20172023
Queue J962
J962
SolarMISODesoto100 MW20182022
Queue 25-IC-1337
25-IC-1337
Solar + BatterySoutheastWayne100 MW20252028
Queue IC-1244susp.
IC-1244
SolarSoutheastNewton100 MW20242029
Queue 313
313
SolarSoutheastMonroe100 MW20172026
Surplus; J908
S1116
BatteryMISOTallahatchie100 MW20252027
Queue J1294
J1294
SolarMISOSunflower99 MW20192023
Queue J1144
J1144
SolarMISOCovington96 MW20182022
Queue 530
530
Solar + BatterySoutheastPinola90 MW20232028
Queue J3590
J3590
SolarMISOHumphreys75 MW20242028
Queue 671
671
Solar + BatterySoutheastMonroe75 MW20242029
Queue 522
522
SolarSoutheastChoctaw67 MW20222026
Queue 314
314
SolarSoutheastMonroe60 MW20172021
Queue J3592
J3592
WindMISOSunflower57 MW20242028
Queue 656
656
GasSoutheastBenton54 MW20242030
Queue J791
J791
SolarMISOLamar52 MW20172020
Queue J1747
J1747
SolarMISOMadison50 MW20202024
Queue 424
424
BatterySoutheastClay50 MW20202026
Queue 519
519
SolarSoutheastMarshall50 MW20222029
Queue IC-1203
IC-1203
SolarSoutheastJasper44 MW20232028
Queue 25-IC-1316
25-IC-1316
GasSoutheastKemper25 MW20252027

See 61 operating plants in Mississippi · Regions: MISO, Non-ISO Southeast.

Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).