State queue · Missouri

Missouri interconnection queue

124 proposed generation and storage projects — 124 active and 0 suspended — are in Missouri's interconnection queue, primarily in the MISO, totaling 29.65 GW of requested capacity. Gas leads with 8.35 GW.

124
Proposed projects
29.65 GW
Requested capacity
Gas
Largest resource type
2027
Median planned online year

Requested capacity by resource type

Gas 28.1%Solar 26.7%Battery 19.6%Wind 11.6%Solar + Battery 7.8%Other 5.6%Coal 0.4%Hydro 0.2%

Proposed projects by resource type

Also in the queue (too few for a dedicated page): Other (4), Hydro (1).

All proposed projects in Missouri

TypeRegion
Queue J3996
J3996
GasMISOSt. Charles2.22 GW20252030
Queue GI-83
GI-83
WindSoutheastRandolph1.02 GW20192027
Queue J1490
J1490
OtherMISORandolph1.00 GW20192024
Replacing 864 MW of coal with Natural Gas Generators; Castle Bluff
R1047
GasMISOSt. Louis824 MW20242025
Queue GEN-2024-207
GEN-2024-207
GasSPPJackson778.6 MW20252029
Queue GI-122
GI-122
WindSoutheastRandolph500 MW20242028
Queue J1488
J1488
OtherMISORandolph500 MW20192024
Queue GI-101
GI-101
GasSoutheastClinton460 MW20222027
Queue GI-121
GI-121
GasSoutheastRandolph460 MW20242030
Queue GI-126
GI-126
GasSoutheastRandolph460 MW20252029
Queue GI-128
GI-128
GasSoutheastClinton460 MW20252030
Queue GI-131
GI-131
GasSoutheastRandolph460 MW20252030
Queue GI-132
GI-132
GasSoutheastButler460 MW20252030
Queue ERAS-2025-007
ERAS-2025-007
GasSPPNodaway450.6 MW20252030
Queue ERAS-2025-013
ERAS-2025-013
GasSPPNodaway450.6 MW20252030
Queue J1026
J1026
WindMISOAudrain400 MW20182023
Queue GEN-2017-108
GEN-2017-108
SolarSPPHenry400 MW20172027
Queue GEN-2025-SR1
GEN-2025-SR1
BatterySPPHenry400 MW20252027
Queue GEN-2024-289
GEN-2024-289
SolarSPPHenry350 MW20252029
Union Electric Company d/b/a Ameren Missouri project
E0013
SolarMISOSullivan310.2 MW20252028
Queue J1025
J1025
WindMISOKnox300 MW20182025
Queue J1836
J1836
SolarMISOCallaway300 MW20202025
Queue J2205
J2205
Solar + BatteryMISOCallaway300 MW20212024
Queue J3199
J3199
Solar + BatteryMISOAdair300 MW20222026
Queue J3518
J3518
BatteryMISOGasconade300 MW20242028
Queue J3758
J3758
SolarMISOMacon300 MW20242028
Queue J3957
J3957
SolarMISOSullivan300 MW20252029
Queue J976
J976
SolarMISOWarren300 MW20182024
Queue GEN-2022-073
GEN-2022-073
BatterySPPClay300 MW20222030
Queue GEN-2024-170
GEN-2024-170
BatterySPPCass280 MW20252028
Union Electric Company d/b/a Ameren Missouri project
E0017
BatteryMISOLincoln257.9 MW20252028
Queue J1145
J1145
SolarMISOCallaway250 MW20182024
Queue J2691
J2691
Solar + BatteryMISOBollinger250 MW20222027
Queue J3352
J3352
BatteryMISOCape Girardeau250 MW20242027
Queue J3929
J3929
WindMISOAudrain250 MW20252030
Queue ERAS-2025-034
ERAS-2025-034
GasSPPJasper250 MW20252030
Queue GEN-2024-217
GEN-2024-217
BatterySPPJackson250 MW20252029
Queue GEN-2024-370
GEN-2024-370
BatterySPPClay250 MW20252028
Queue GI-95
GI-95
WindSoutheastDade247 MW20202026
Queue J476
J476
WindMISOAtchison246 MW20152021
Queue GI-120
GI-120
SolarSoutheastRandolph245 MW20242031
Queue J4001
J4001
SolarMISOMarion245 MW20252030
Queue GI-53
GI-53
WindSoutheastNodaway238 MW20162018
Queue GI-61
GI-61
WindSoutheastNodaway230 MW20172019
Queue GEN-2024-206
GEN-2024-206
GasSPPJackson226.3 MW20252026
Queue J1034
J1034
SolarMISOStoddard225 MW20182024
Queue J2050
J2050
SolarMISOMacon208.4 MW20222024
Queue J1087
J1087
SolarMISOScott200 MW20182023
Queue J1107
J1107
SolarMISOCape Girardeau200 MW20182023
Queue J1299
J1299
SolarMISOScott200 MW20192025
Queue J1519
J1519
SolarMISOBollinger200 MW20202025
Queue J2238
J2238
Solar + BatteryMISOMaries200 MW20252024
Queue J2265
J2265
Solar + BatteryMISOBollinger200 MW20252024
Queue J2524
J2524
SolarMISOStoddard200 MW20222026
Queue J2806
J2806
SolarMISOWarren200 MW20222026
Queue J3436
J3436
SolarMISODaviess200 MW20242028
Queue J3440
J3440
BatteryMISODaviess200 MW20242028
Queue J3919
J3919
SolarMISOLincoln200 MW20252030
Queue J3959
J3959
SolarMISOGrundy200 MW20252029
Queue J4090
J4090
SolarMISOSchuyler200 MW20252030
Queue J956
J956
SolarMISORalls200 MW20182024
Queue GEN-2019-016
GEN-2019-016
SolarSPPPolk200 MW20192029
Queue GEN-2022-142
GEN-2022-142
BatterySPPClay200 MW20232030
Queue GEN-2022-144
GEN-2022-144
BatterySPPJackson200 MW20232030
Queue GEN-2023-033
GEN-2023-033
BatterySPPClay200 MW20232028
Queue GEN-2024-074
GEN-2024-074
BatterySPPJackson200 MW20242028
Queue GEN-2024-175
GEN-2024-175
BatterySPPGreene200 MW20252028
Surplus; J944
S1117
BatteryMISONew Madrid200 MW20252028
Queue GEN-2024-259
GEN-2024-259
Solar + BatterySPPBarton199.8 MW20252029
Queue GEN-2024-260
GEN-2024-260
BatterySPPBuchanan199.8 MW20252029
Queue GEN-2024-167
GEN-2024-167
BatterySPPRay199 MW20252030
Queue GEN-2024-181
GEN-2024-181
BatterySPPGreene199 MW20252029
Queue GEN-2024-352
GEN-2024-352
BatterySPPJackson199 MW20252030
Queue J1948
J1948
SolarMISOMarion195 MW20222024
Queue J2288
J2288
SolarMISORalls175 MW20252025
Queue GEN-2024-055
GEN-2024-055
SolarSPPVernon175 MW20242029
Queue GEN-2024-084
GEN-2024-084
BatterySPPLawrence167 MW20242028
Queue J3442
J3442
SolarMISOScott156 MW20242028
Queue J1268
J1268
SolarMISOLincoln150 MW20192023
Queue J2142
J2142
Solar + BatteryMISOAdair150 MW20212024
Queue J2155
J2155
SolarMISONew Madrid150 MW20222024
Queue J3505
J3505
BatteryMISOBollinger150 MW20242028
Queue GEN-2020-072
GEN-2020-072
Solar + BatterySPPHenry150 MW20202029
Queue GEN-2020-088
GEN-2020-088
SolarSPPJasper150 MW20202028
Queue GEN-2023-170
GEN-2023-170
BatterySPPChariton150 MW20232028
Queue GEN-2023-171
GEN-2023-171
BatterySPPJackson150 MW20232028
Queue GEN-2024-088
GEN-2024-088
GasSPPGreene145 MW20242027
Queue J2593
J2593
Solar + BatteryMISOGasconade140 MW20222026
Queue J3229
J3229
Solar + BatteryMISOMaries140 MW20222026
Queue GEN-2017-188
GEN-2017-188
SolarSPPBarry130 MW20172026
Queue GEN-2024-054
GEN-2024-054
SolarSPPCooper120 MW20242029
Queue J2382
J2382
Solar + BatteryMISORandolph115 MW20222026
Queue GI-86
GI-86
SolarSoutheastRandolph100 MW20192027
Queue GI-90
GI-90
SolarSoutheastRandolph100 MW20202027
Queue GI-93
GI-93
SolarSoutheastMacon100 MW20202026
Queue J1352
J1352
SolarMISOMontgomery100 MW20192024
Queue J2179
J2179
SolarMISOMontgomery100 MW20212024
Queue J3736
J3736
BatteryMISOOsage100 MW20242027
Queue GEN-2022-102
GEN-2022-102
BatterySPPClay100 MW20232027
Queue GEN-2023-061
GEN-2023-061
BatterySPPJasper100 MW20232029

Showing the 100 largest of 124 projects by requested capacity.

See 129 operating plants in Missouri · Regions: MISO, SPP, Non-ISO Southeast.

Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).