Nevada · Geothermal
Proposed geothermal projects in Nevada
There are 37 proposed geothermal projects in Nevada's interconnection queue, totaling 4.16 GW of requested capacity. The largest is Queue 25-00406 at 600 MW, and the median planned online year is 2029.
37
Proposed projects
4.16 GW
Requested capacity
112.5 MW
Average project size
2029
Median planned online year
All proposed geothermal projects in Nevada
| Type | ||||
|---|---|---|---|---|
| Queue 25-00406 25-00406 | Geothermal | 600 MW | 2025 | 2029 |
| Queue 25-00409 25-00409 | Geothermal | 600 MW | 2025 | 2033 |
| Queue 25-00412 25-00412 | Geothermal | 600 MW | 2025 | 2032 |
| Queue Company LM Company LM | Geothermal | 230 MW | 2021 | 2029 |
| Queue 25-00404 25-00404 | Geothermal | 200 MW | 2025 | 2029 |
| Queue 25-00405 25-00405 | Geothermal | 200 MW | 2025 | 2029 |
| Queue 25-00407 25-00407 | Geothermal | 200 MW | 2025 | 2032 |
| Queue 25-00408 25-00408 | Geothermal | 200 MW | 2025 | 2033 |
| Queue 25-00410 25-00410 | Geothermal | 200 MW | 2025 | 2031 |
| Queue 25-00411 25-00411 | Geothermal | 200 MW | 2025 | 2032 |
| Queue Company LB Company LB | Geothermal | 115 MW | 2021 | 2029 |
| Queue 25-00392 25-00392 | Geothermal | 70 MW | 2025 | 2028 |
| Queue Company HN Company HN | Geothermal | 45 MW | 2017 | 2026 |
| Queue Company LT Company LT | Geothermal | 40 MW | 2021 | 2026 |
| Queue 25-00389 25-00389 | Geothermal | 38.5 MW | 2025 | 2029 |
| Queue 25-00391 25-00391 | Geothermal | 38.5 MW | 2025 | 2028 |
| Queue Company EV Company EV | Geothermal | 38.5 MW | 2010 | 2026 |
| Queue Company HU Company HU | Geothermal | 38.5 MW | 2017 | 2023 |
| Queue Company KG Company KG | Geothermal | 38.5 MW | 2020 | 2027 |
| Queue Company KH Company KH | Geothermal | 38.5 MW | 2020 | 2022 |
| Queue Company KI Company KI | Geothermal | 38.5 MW | 2020 | 2025 |
| Queue Company KJ Company KJ | Geothermal | 38.5 MW | 2020 | 2023 |
| Queue Company KY Company KY | Geothermal | 38.5 MW | 2021 | 2027 |
| Queue Company KZ Company KZ | Geothermal | 38.5 MW | 2021 | 2027 |
| Queue Company QK Company QK | Geothermal | 38.5 MW | 2023 | 2030 |
| Queue 25-00425 25-00425 | Geothermal | 31 MW | 2025 | 2030 |
| Queue Company LR Company LR | Geothermal | 29 MW | 2021 | 2024 |
| Queue 25N-SG3 25N-SG3 | Geothermal | 20 MW | 2025 | 2030 |
| Queue 25N-SG4 25N-SG4 | Geothermal | 20 MW | 2025 | 2030 |
| Queue 25N-SG5 25N-SG5 | Geothermal | 20 MW | 2025 | 2030 |
| Queue Company RA Company RA | Geothermal | 20 MW | 2024 | 2029 |
| Queue Company RB Company RB | Geothermal | 20 MW | 2024 | 2029 |
| Queue Company RD Company RD | Geothermal | 19.9 MW | 2025 | 2030 |
| Queue 25N-SG2 25N-SG2 | Geothermal | 19.8 MW | 2025 | 2029 |
| Queue Company MM Company MM | Geothermal | 19.8 MW | 2021 | 2025 |
| Queue 25N-SG7 25N-SG7 | Geothermal | 16 MW | 2025 | 2029 |
| Queue Company KO Company KO | Geothermal | 4.8 MW | 2020 | 2027 |
Browse Nevada's full interconnection queue. Compare with operating capacity: 26 operating geothermal plants in Nevada. Nationwide: Geothermal plants nationwide.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).