State queue · North Dakota
North Dakota interconnection queue
62 proposed generation and storage projects — 62 active and 0 suspended — are in North Dakota's interconnection queue, primarily in the SPP, totaling 14.50 GW of requested capacity. Wind leads with 5.45 GW.
62
Proposed projects
14.50 GW
Requested capacity
Wind
Largest resource type
2028
Median planned online year
Requested capacity by resource type
Wind 37.6%Gas 23.1%Battery 14.7%Solar 10.6%Solar + Battery 8.1%Other 6.0%
Proposed projects by resource type
Wind projects26 · 5.45 GWGas projects7 · 3.34 GWBattery projects12 · 2.14 GWSolar projects10 · 1.53 GW
Also in the queue (too few for a dedicated page): Solar + Battery (3), Other (4).
All proposed projects in North Dakota
| Type | ||||
|---|---|---|---|---|
| Queue ERAS-2025-011 ERAS-2025-011 | Gas | 750 MW | 2025 | 2030 |
| Queue ERAS-2025-012 ERAS-2025-012 | Gas | 750 MW | 2025 | 2030 |
| Queue GEN-2024-081 GEN-2024-081 | Gas | 745 MW | 2024 | 2029 |
| Queue GEN-2024-082 GEN-2024-082 | Gas | 745 MW | 2024 | 2030 |
| Queue J4105 J4105 | Solar + Battery | 500 MW | 2025 | 2028 |
| Queue J4106 J4106 | Solar + Battery | 500 MW | 2025 | 2027 |
| Queue J3163 J3163 | Other | 479 MW | 2022 | 2028 |
| Red Butte Wind E0027 | Wind | 456.8 MW | 2025 | 2028 |
| Queue GEN-2024-141 GEN-2024-141 | Wind | 424 MW | 2025 | 2031 |
| Queue GI-1404 GI-1404 | Wind | 383 MW | 2014 | — |
| Queue MPC04000 MPC04000 | Wind | 300 MW | 2019 | 2023 |
| Queue J3280 J3280 | Wind | 300 MW | 2024 | 2028 |
| Queue GEN-2024-331 GEN-2024-331 | Battery | 300 MW | 2025 | 2028 |
| Queue MPC04500 MPC04500 | Wind | 258.4 MW | 2023 | 2028 |
| Queue GEN-2018-067 GEN-2018-067 | Wind | 255 MW | 2018 | 2028 |
| Queue GI-1503 GI-1503 | Wind | 250.7 MW | 2015 | — |
| Queue MPC03800 MPC03800 | Wind | 250 MW | 2019 | 2027 |
| Queue J1040 J1040 | Wind | 250 MW | 2018 | 2023 |
| Queue GEN-2022-010 GEN-2022-010 | Other | 250 MW | 2022 | 2025 |
| Queue GEN-2022-083 GEN-2022-083 | Gas | 250 MW | 2022 | 2025 |
| Queue GEN-2024-328 GEN-2024-328 | Battery | 250 MW | 2025 | 2028 |
| Queue J3787 J3787 | Solar | 247 MW | 2024 | 2028 |
| Queue GEN-2024-326 GEN-2024-326 | Battery | 225 MW | 2025 | 2028 |
| Queue MPC04600 MPC04600 | Battery | 208.6 MW | 2025 | 2028 |
| Queue MPC04400 MPC04400 | Wind | 205.9 MW | 2022 | 2024 |
| Queue GEN-2016-004 GEN-2016-004 | Wind | 202 MW | 2016 | 2027 |
| Queue J1588 J1588 | Solar | 200 MW | 2024 | 2026 |
| Queue J2080 J2080 | Wind | 200 MW | 2021 | 2024 |
| Queue J2250 J2250 | Wind | 200 MW | 2021 | 2024 |
| Queue J3522 J3522 | Solar | 200 MW | 2024 | 2028 |
| Queue J3833 J3833 | Wind | 200 MW | 2024 | 2028 |
| Queue GEN-2024-327 GEN-2024-327 | Battery | 200 MW | 2025 | 2028 |
| Queue GEN-2024-329 GEN-2024-329 | Battery | 200 MW | 2025 | 2028 |
| Surplus; J1588 S1079 | Battery | 200 MW | 2025 | 2028 |
| Queue GEN-2024-284 GEN-2024-284 | Solar | 199 MW | 2025 | 2028 |
| Queue GI-1502 GI-1502 | Wind | 181.7 MW | 2015 | — |
| Queue GEN-2024-034 GEN-2024-034 | Battery | 175 MW | 2024 | 2029 |
| Queue J4170 J4170 | Solar + Battery | 172 MW | 2025 | 2029 |
| Queue GI-1508 GI-1508 | Wind | 172 MW | 2015 | — |
| Queue MPC03600 MPC03600 | Solar | 170 MW | 2018 | 2027 |
| Queue GEN-2023-SR4 GEN-2023-SR4 | Battery | 170 MW | 2022 | 2026 |
| Queue MPC03900 MPC03900 | Wind | 151.2 MW | 2019 | 2027 |
| Queue J2502 J2502 | Wind | 150 MW | 2022 | 2025 |
| Queue GEN-2019-037 GEN-2019-037 | Solar | 150 MW | 2019 | 2023 |
| Queue GEN-2020-091 GEN-2020-091 | Solar | 150 MW | 2020 | 2029 |
| Queue GI-1509 GI-1509 | Wind | 150 MW | 2015 | — |
| Queue MPC03700 MPC03700 | Solar | 130 MW | 2018 | 2027 |
| Queue GEN-2022-009 GEN-2022-009 | Other | 125 MW | 2022 | 2025 |
| Replace 103.1 MW of Heskett Units 1 & 2 with One (1) General Electric synchronous combustion turbine; Heskett 1 & 2 R1000 | Gas | 103.1 MW | 2019 | 2022 |
| Queue J2097 J2097 | Wind | 100 MW | 2021 | 2025 |
| Queue J2157 J2157 | Wind | 100 MW | 2021 | 2025 |
| Queue J3070 J3070 | Wind | 100 MW | 2022 | 2025 |
| Queue GEN-2017-214 GEN-2017-214 | Wind | 100 MW | 2017 | 2030 |
| Queue GEN-2017-215 GEN-2017-215 | Wind | 100 MW | 2017 | 2030 |
| Queue GEN-2024-359 GEN-2024-359 | Battery | 100 MW | 2025 | 2030 |
| Queue J2913 J2913 | Battery | 90 MW | 2022 | 2025 |
| Queue J4077 J4077 | Solar | 45 MW | 2025 | 2030 |
| Queue J4070 J4070 | Solar | 40 MW | 2025 | 2030 |
| Queue GEN-2024-SR12 GEN-2024-SR12 | Battery | 20 MW | 2024 | 2026 |
| Queue G150 G150 | Other | 12 MW | 2001 | 2002 |
| Queue GEN-2025-GR5 GEN-2025-GR5 | Wind | 7.7 MW | 2025 | — |
| Blaise Energy project GI-1103 | Gas | 0.8 MW | 2011 | 2011 |
See 60 operating plants in North Dakota · Regions: SPP, MISO, Non-ISO West.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).