North Dakota · Battery

Proposed battery projects in North Dakota

There are 8 proposed battery projects in North Dakota's interconnection queue, totaling 1.37 GW of requested capacity. The largest is Queue MPC04600 at 208.6 MW, and the median planned online year is 2028.

8
Proposed projects
1.37 GW
Requested capacity
171.1 MW
Average project size
2028
Median planned online year

All proposed battery projects in North Dakota

TypeRegionIA Status
Queue MPC04600
MPC04600
BatteryMISOEddyIn Progress (unknown study)208.6 MW20252028
Queue GEN-2024-327
GEN-2024-327
BatterySPPWardSystem Impact Study200 MW20252028
Queue GEN-2024-329
GEN-2024-329
BatterySPPWilliamsSystem Impact Study200 MW20252028
Surplus; J1588
S1079
BatteryMISOCass200 MW20252028
Queue GEN-2023-SR4
GEN-2023-SR4
BatterySPPBurkeIA Executed170 MW20222026
Queue GEN-2026-SR6
GEN-2026-SR6
BatterySPPSouth Heart150 MW20262028
Queue GEN-2026-SR7
GEN-2026-SR7
BatterySPPSouth Heart150 MW20262028
Queue J2913
J2913
BatteryMISOSargentCluster Study90 MW20222025

Browse North Dakota's full interconnection queue. Nationwide: Storage plants nationwide.

Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition). Data: LBNL backbone through December 31, 2025; ISO-region statuses refreshed monthly (last: July 2026); non-ISO West and Southeast as of the LBNL edition.