North Dakota · Battery

Proposed battery projects in North Dakota

There are 12 proposed battery projects in North Dakota's interconnection queue, totaling 2.14 GW of requested capacity. The largest is Queue GEN-2024-331 at 300 MW, and the median planned online year is 2028.

12
Proposed projects
2.14 GW
Requested capacity
178.2 MW
Average project size
2028
Median planned online year

All proposed battery projects in North Dakota

TypeRegionIA Status
Queue GEN-2024-331
GEN-2024-331
BatterySPPDunnSystem Impact Study300 MW20252028
Queue GEN-2024-328
GEN-2024-328
BatterySPPSlopeSystem Impact Study250 MW20252028
Queue GEN-2024-326
GEN-2024-326
BatterySPPStarkSystem Impact Study225 MW20252028
Queue MPC04600
MPC04600
BatteryMISOEddyIn Progress (unknown study)208.6 MW20252028
Queue GEN-2024-327
GEN-2024-327
BatterySPPWardSystem Impact Study200 MW20252028
Queue GEN-2024-329
GEN-2024-329
BatterySPPWilliamsSystem Impact Study200 MW20252028
Surplus; J1588
S1079
BatteryMISOCass200 MW20252028
Queue GEN-2024-034
GEN-2024-034
BatterySPPSargentSystem Impact Study175 MW20242029
Queue GEN-2023-SR4
GEN-2023-SR4
BatterySPPBurkeIA Executed170 MW20222026
Queue GEN-2024-359
GEN-2024-359
BatterySPPStarkSystem Impact Study100 MW20252030
Queue J2913
J2913
BatteryMISOSargentCluster Study90 MW20222025
Queue GEN-2024-SR12
GEN-2024-SR12
BatterySPPLamoureIA Pending20 MW20242026

Browse North Dakota's full interconnection queue. Nationwide: Storage plants nationwide.

Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).