Tennessee · Battery
Proposed battery projects in Tennessee
There are 6 proposed battery projects in Tennessee's interconnection queue, totaling 747 MW of requested capacity. The largest is Queue 587 at 225 MW, and the median planned online year is 2027.
6
Proposed projects
747 MW
Requested capacity
124.5 MW
Average project size
2027
Median planned online year
All proposed battery projects in Tennessee
| Type | ||||
|---|---|---|---|---|
| Queue 587 587 | Battery | 225 MW | 2023 | 2029 |
| Queue 661 661 | Battery | 200 MW | 2024 | 2026 |
| Queue 25RSC-007 25RSC-007 | Battery | 100 MW | 2025 | 2030 |
| Queue 547 547 | Battery | 100 MW | 2023 | 2026 |
| Queue 643 643 | Battery | 100 MW | 2024 | 2027 |
| Queue 461 461 | Battery | 22 MW | 2020 | 2024 |
Browse Tennessee's full interconnection queue. Nationwide: Storage plants nationwide.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).