Texas · Battery
Proposed battery projects in Texas
There are 739 proposed battery projects in Texas's interconnection queue, totaling 137.87 GW of requested capacity. The largest is Kickstart Energy Storage VI at 1.03 GW, and the median planned online year is 2027.
739
Proposed projects
137.87 GW
Requested capacity
186.6 MW
Average project size
2027
Median planned online year
All proposed battery projects in Texas
| Type | ||||
|---|---|---|---|---|
| Kickstart Energy Storage VI 29INR0218 | Battery | 1.03 GW | 2025 | 2029 |
| Kickstart Energy Storage V 29INR0217 | Battery | 999 MW | 2025 | 2029 |
| Nabla Energy Storage I 27INR0571 | Battery | 750 MW | 2025 | 2028 |
| Nabla Energy Storage II 28INR0466 | Battery | 750 MW | 2025 | 2028 |
| Howard Road BESS 29INR0173 | Battery | 617.6 MW | 2025 | 2028 |
| Comanche BESS 27INR0365 | Battery | 614.4 MW | 2024 | 2028 |
| Symphony BESS 26INR0466 | Battery | 612 MW | 2025 | 2028 |
| Lavita BESS 26INR0465 | Battery | 606 MW | 2024 | 2028 |
| Hobby BESS I 26INR0546 | Battery | 602.6 MW | 2024 | 2027 |
| Capoterra BESSsusp. 25INR0088 | Battery | 600 MW | 2022 | — |
| Tempesta BESSsusp. 25INR0090 | Battery | 600 MW | 2022 | — |
| Brittlebush BESSsusp. 25INR0095 | Battery | 597.1 MW | 2022 | — |
| TOCE TX BESS 2 26INR0334 | Battery | 523.4 MW | 2024 | 2027 |
| Knight Airport BESS I 26INR0545 | Battery | 522.5 MW | 2024 | 2027 |
| Avalon BESS 26INR0375 | Battery | 522.1 MW | 2023 | 2026 |
| Falcon BESS 29INR0169 | Battery | 516.7 MW | 2025 | 2028 |
| Ochoa Energy Storage II 27INR0235 | Battery | 516.6 MW | 2024 | 2029 |
| Catamount Storage 28INR0097 | Battery | 515.4 MW | 2024 | 2028 |
| Seven Angels Energy Storage I 28INR0472 | Battery | 514 MW | 2025 | 2028 |
| Seven Angels Energy Storage II 28INR0473 | Battery | 514 MW | 2025 | 2028 |
| Diamante BESS 27INR0115 | Battery | 513.7 MW | 2024 | 2028 |
| Midnight Sun Energy Storage 24INR0442 | Battery | 510 MW | 2022 | 2028 |
| Crescent C BESS 26INR0089 | Battery | 508.3 MW | 2023 | 2028 |
| Bayside BESSsusp. 24INR0237 | Battery | 507.8 MW | 2022 | — |
| Point Mountain Storagesusp. 26INR0055 | Battery | 507.2 MW | — | — |
| Freedom Falcon BESS 26INR0107 | Battery | 501.9 MW | 2023 | 2028 |
| Orbit Energy Storage 27INR0082 | Battery | 501.9 MW | 2023 | 2027 |
| Millsing BESS 27INR0190 | Battery | 501.6 MW | 2024 | 2028 |
| Betel Storage I 26INR0630 | Battery | 500 MW | 2025 | 2026 |
| Betel Storage II 26INR0633 | Battery | 500 MW | 2025 | 2026 |
| GAMAY ENERGY STORAGE 26INR0417 | Battery | 418.6 MW | 2024 | 2027 |
| Bypass BESS II 26INR0525 | Battery | 416 MW | 2024 | 2027 |
| BRP Artemis BESS 24INR0130 | Battery | 411.3 MW | 2021 | 2028 |
| BRP Snowdon BESS 23INR0330 | Battery | 410.9 MW | 2021 | 2028 |
| BRP Mekong BESS 24INR0135 | Battery | 409.9 MW | 2021 | 2027 |
| Wilson BESS 28INR0285 | Battery | 409.7 MW | 2025 | 2028 |
| McCamey's Castle Battery 25INR0557 | Battery | 409.6 MW | 2023 | 2027 |
| Beacon Storage 23INR0127 | Battery | 408.7 MW | 2021 | 2029 |
| Sigma Storage 23INR0126 | Battery | 408.4 MW | 2021 | 2029 |
| LUND STORAGE CENTER 1 26INR0045 | Battery | 407.6 MW | 2023 | 2026 |
| 18-BRAVO BESS 28INR0327 | Battery | 407 MW | 2025 | 2028 |
| Claire BESS 24INR0500 | Battery | 406 MW | 2023 | 2027 |
| Bernice Energy Storage 27INR0294 | Battery | 402.8 MW | 2024 | 2027 |
| Merope BESS 24INR0157 | Battery | 402.4 MW | 2021 | 2028 |
| Iron Belt Energy Storage 25INR0208 | Battery | 401.9 MW | 2023 | 2027 |
| CORRUSCANT BESS 27INR0195 | Battery | 401.4 MW | 2024 | 2027 |
| Aldrin 345 BESS 25INR0425 | Battery | 362 MW | 2023 | 2027 |
| Wildflower Storage 28INR0292 | Battery | 359.1 MW | 2025 | 2028 |
| Brookesmith Storage 28INR0166 | Battery | 351 MW | 2025 | 2029 |
| Rabbit Hollow Energy Storage 28INR0119 | Battery | 341.8 MW | 2024 | 2028 |
| Andromeda Storage IIsusp. 26INR0517 | Battery | 320 MW | 2024 | — |
| Andromeda Storage IIBsusp. 26INR0540 | Battery | 320 MW | 2024 | — |
| Jade Flash Storagesusp. 26INR0516 | Battery | 320 MW | 2024 | — |
| Jade Thunder Storagesusp. 26INR0539 | Battery | 320 MW | 2024 | — |
| Radian Storage IIsusp. 26INR0518 | Battery | 320 MW | 2024 | — |
| Radian Storage IIBsusp. 26INR0541 | Battery | 320 MW | 2024 | — |
| Elio BESS 25INR0103 | Battery | 317.2 MW | 2022 | 2027 |
| White Bright BESS 26INR0605 | Battery | 313.7 MW | 2025 | 2029 |
| Diablo Campo Storage 27INR0149 | Battery | 313.5 MW | 2024 | 2029 |
| Wild Paw Storage 28INR0075 | Battery | 313.2 MW | 2024 | 2028 |
| Royal River BESS 24INR0282 | Battery | 310.7 MW | 2022 | 2027 |
| Red Egret BESS 24INR0281 | Battery | 310.6 MW | 2022 | 2026 |
| Oak Tree Energy Storage 27INR0091 | Battery | 310.2 MW | 2023 | 2029 |
| Two Forks BESS 24INR0198 | Battery | 309.8 MW | 2022 | 2027 |
| Platinum Storage 22INR0554 | Battery | 309.5 MW | 2021 | 2026 |
| Clay County Yang Storage 26INR0612 | Battery | 307.5 MW | 2024 | 2028 |
| Larkspur Energy Storage 23INR0340 | Battery | 307.5 MW | 2021 | 2027 |
| 18-ALPHA BESS 28INR0328 | Battery | 307.4 MW | 2025 | 2028 |
| Mensa BESS 22INR0365 | Battery | 307.4 MW | 2020 | 2027 |
| Haute Stockagesusp. 26INR0282 | Battery | 307.3 MW | 2023 | 2027 |
| Beaujolais BESSsusp. 26INR0286 | Battery | 307.2 MW | 2023 | 2026 |
| Team Ranch Storage 24INR0763 | Battery | 307.2 MW | 2024 | 2027 |
| Axtell BESS 28INR0157 | Battery | 306.9 MW | 2024 | 2029 |
| Copperleaf Energy Storage 28INR0118 | Battery | 306.5 MW | 2024 | 2029 |
| Gilleys Energy Storage 25INR0656 | Battery | 306.4 MW | 2024 | 2028 |
| McCrae Energy Storage 25INR0661 | Battery | 306.4 MW | 2024 | 2028 |
| O'Bannion Energy Storage 25INR0657 | Battery | 306.4 MW | 2024 | 2028 |
| Southfork Energy Storage 25INR0653 | Battery | 306.4 MW | 2024 | 2028 |
| Wooderson Energy Storage 25INR0660 | Battery | 306.4 MW | 2024 | 2028 |
| Blue Skies BESS 25INR0046 | Battery | 306.3 MW | 2022 | 2027 |
| Spur Energy Storage 28INR0278 | Battery | 306.3 MW | 2025 | 2028 |
| Aurora Energy Storage 28INR0277 | Battery | 306.2 MW | 2025 | 2028 |
| Furay Battery Energy Storage System 24INR0413 | Battery | 304 MW | 2022 | 2027 |
| NavBoot BESS 25INR0375 | Battery | 303.7 MW | 2023 | 2026 |
| BRP Aras BESS 23INR0272 | Battery | 303.6 MW | 2021 | 2028 |
| Juanita Creek BESS 29INR0151 | Battery | 303.6 MW | 2025 | 2031 |
| Wander Waters BESS 27INR0207 | Battery | 303.5 MW | 2024 | 2027 |
| Brantley Branch Batt 22INR0332 | Battery | 302.4 MW | 2020 | 2029 |
| Outrider BESS 28INR0288 | Battery | 302 MW | 2025 | 2028 |
| BRP Passu BESS 23INR0139 | Battery | 301.8 MW | 2020 | 2028 |
| Dairyland Storage 27INR0451 | Battery | 301.8 MW | 2025 | 2029 |
| Simsboro Storage 29INR0119 | Battery | 301.6 MW | 2025 | 2029 |
| Crater BESS 22INR0347 | Battery | 301.5 MW | 2020 | 2028 |
| Quela BESS 22INR0423 | Battery | 301.4 MW | 2020 | 2027 |
| Rubicon Power BESS 27INR0096 | Battery | 301.4 MW | 2023 | 2026 |
| Seine BESS 23INR0140 | Battery | 301.2 MW | 2020 | 2027 |
| Cernan BESS 27INR0392 | Battery | 301.1 MW | 2025 | 2027 |
| Acker BESS 25INR0460 | Battery | 301 MW | 2023 | 2028 |
| Great Rock BESS 25INR0230 | Battery | 300.9 MW | 2022 | 2027 |
| Queue GEN-2022-139 GEN-2022-139 | Battery | 300 MW | 2023 | 2030 |
Showing the 100 largest of 739 projects by requested capacity.
Browse Texas's full interconnection queue. Compare with operating capacity: 115 operating storage plants in Texas. Nationwide: Storage plants nationwide.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).