Utah · Battery
Proposed battery projects in Utah
There are 33 proposed battery projects in Utah's interconnection queue, totaling 5.84 GW of requested capacity. The largest is Oquirrh Energy Storage, LLC project at 500 MW, and the median planned online year is 2026.
33
Proposed projects
5.84 GW
Requested capacity
177.1 MW
Average project size
2026
Median planned online year
All proposed battery projects in Utah
| Type | ||||
|---|---|---|---|---|
| Oquirrh Energy Storage, LLC project C2-10 | Battery | 500 MW | 2022 | 2031 |
| Queue PIS087 PIS087 | Battery | 500 MW | 2024 | 2027 |
| Queue T2-084 T2-084 | Battery | 500 MW | 2025 | 2029 |
| Queue T2-083 T2-083 | Battery | 400 MW | 2025 | 2030 |
| Queue T2-075 T2-075 | Battery | 300 MW | 2025 | 2027 |
| Queue T2-061 T2-061 | Battery | 225 MW | 2025 | 2027 |
| Intermountain Power Agency project Q83 | Battery | 220 MW | 2021 | 2024 |
| Queue S0017 S0017 | Battery | 200 MW | 2022 | 2026 |
| Queue S0037 S0037 | Battery | 200 MW | 2025 | 2027 |
| Queue C3-171 C3-171 | Battery | 199.9 MW | 2023 | 2026 |
| Queue C2-109 C2-109 | Battery | 199 MW | 2022 | 2025 |
| Queue C2-110 C2-110 | Battery | 199 MW | 2022 | 2025 |
| Dominguez Grid, LLC project C2-28 | Battery | 199 MW | 2022 | 2031 |
| Queue PIS025 PIS025 | Battery | 199 MW | 2022 | 2025 |
| Queue PIS026 PIS026 | Battery | 199 MW | 2022 | 2025 |
| Queue PIS088 PIS088 | Battery | 199 MW | 2024 | 2028 |
| Queue T2-080 T2-080 | Battery | 160 MW | 2025 | 2027 |
| Queue S0033 S0033 | Battery | 122 MW | 2024 | 2027 |
| Hunter Utah Storage Acquisitions, LLC project S0015 | Battery | 100 MW | 2022 | 2027 |
| Queue S0036 S0036 | Battery | 100 MW | 2025 | 2027 |
| Escalante BESS I LLC project S0007 | Battery | 80 MW | 2022 | 2025 |
| Escalante BESS II LLC project S0008 | Battery | 80 MW | 2022 | 2024 |
| Escalante BESS III LLC project S0009 | Battery | 80 MW | 2022 | 2024 |
| Enterprise Storage LLC project S0010 | Battery | 80 MW | 2022 | 2025 |
| Granite Mountain BESS East LLC project S0011 | Battery | 80 MW | 2022 | 2025 |
| Iron Springs BESS LLC project S0013 | Battery | 80 MW | 2022 | 2025 |
| Sigurd Storage Acquisitions, L.L.C. project S0016 | Battery | 80 MW | 2022 | 2027 |
| Queue S0031 S0031 | Battery | 80 MW | 2024 | 2026 |
| Queue S0034 S0034 | Battery | 80 MW | 2024 | 2026 |
| Queue S0018 S0018 | Battery | 75 MW | 2022 | 2026 |
| Queue S0014 S0014 | Battery | 58 MW | 2022 | 2026 |
| Granite Mountain BESS West LLC project S0012 | Battery | 50 MW | 2022 | 2024 |
| Revolve Vernal BESS, LLC projectsusp. C2-209 | Battery | 20 MW | 2022 | 2026 |
Browse Utah's full interconnection queue. Nationwide: Storage plants nationwide.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).