Utah · Solar + Battery
Proposed solar + battery projects in Utah
There are 73 proposed solar + battery projects in Utah's interconnection queue, totaling 17.82 GW of requested capacity. The largest is Intermountain Power Agency project at 1.00 GW, and the median planned online year is 2027.
73
Proposed projects
17.82 GW
Requested capacity
244.1 MW
Average project size
2027
Median planned online year
All proposed solar + battery projects in Utah
| Type | ||||
|---|---|---|---|---|
| Intermountain Power Agency project Q93 | Solar + Battery | 1.00 GW | 2022 | 2025 |
| Intermountain Power Agency project Q105 | Solar + Battery | 600 MW | 2023 | 2028 |
| Faraday Interconnection LLC project 838 | Solar + Battery | 525 MW | 2016 | 2025 |
| Queue NC5-010 NC5-010 | Solar + Battery | 500 MW | 2024 | 2028 |
| Queue C3-036 C3-036 | Solar + Battery | 500 MW | 2023 | 2027 |
| Queue NC5-001 NC5-001 | Solar + Battery | 480 MW | 2015 | 2028 |
| Drunkards Wash Energy, LLC project C1-11 | Solar + Battery | 450 MW | 2021 | 2028 |
| Green River Solar I, LLC project 787 | Solar + Battery | 400 MW | 2016 | 2024 |
| Mosida Solar, LLC projectsusp. C1-50 | Solar + Battery | 400 MW | 2021 | 2024 |
| Queue T2-076 T2-076 | Solar + Battery | 400 MW | 2025 | 2027 |
| Queue T2-085 T2-085 | Solar + Battery | 400 MW | 2025 | 2030 |
| Intermountain Power Agency project Q104 | Solar + Battery | 400 MW | 2023 | 2028 |
| Intermountain Power Agency project Q50 | Solar + Battery | 400 MW | 2016 | 2021 |
| Intermountain Power Agency project Q51 | Solar + Battery | 400 MW | 2016 | 2022 |
| Intermountain Power Agency project Q90 | Solar + Battery | 400 MW | 2022 | 2027 |
| Intermountain Power Agency project Q94 | Solar + Battery | 400 MW | 2022 | 2026 |
| Intermountain Power Agency project Q114 | Solar + Battery | 345 MW | 2025 | 2029 |
| Queue T2-052 T2-052 | Solar + Battery | 340 MW | 2025 | 2029 |
| Intermountain Power Agency project Q52 | Solar + Battery | 324 MW | 2016 | 2018 |
| REBU BN, LLC project C1-39 | Solar + Battery | 300 MW | 2021 | 2027 |
| Thirsty Valley Solar Energy LLC projectsusp. C1-51 | Solar + Battery | 300 MW | 2021 | 2024 |
| Queue C2-39 C2-39 | Solar + Battery | 300 MW | 2022 | 2025 |
| Queue C2-72 C2-72 | Solar + Battery | 300 MW | 2022 | 2025 |
| Queue PIS049 PIS049 | Solar + Battery | 300 MW | 2023 | 2026 |
| Queue T2-028 T2-028 | Solar + Battery | 300 MW | 2025 | 2029 |
| Queue T2-056 T2-056 | Solar + Battery | 300 MW | 2025 | 2029 |
| Longroad Development Company, LLC projectsusp. TCS-09 | Solar + Battery | 300 MW | 2017 | 2023 |
| Intermountain Power Agency project Q44 | Solar + Battery | 300 MW | 2013 | 2018 |
| Intermountain Power Agency project Q49 | Solar + Battery | 300 MW | 2015 | 2020 |
| Intermountain Power Agency project Q53 | Solar + Battery | 285 MW | 2016 | 2019 |
| Queue PIS047 PIS047 | Solar + Battery | 275 MW | 2023 | 2027 |
| Queue T2-023 T2-023 | Solar + Battery | 275 MW | 2025 | 2026 |
| Intermountain Power Agency project Q85 | Solar + Battery | 275 MW | 2021 | 2025 |
| Queue T2-053 T2-053 | Solar + Battery | 248 MW | 2025 | 2029 |
| Quicksilver Solar, LLC project C1-34 | Solar + Battery | 200 MW | 2021 | 2027 |
| Queue 785 785 | Solar + Battery | 199 MW | 2025 | 2027 |
| Neptune Solar Energy Park LLC projectsusp. C1-16 | Solar + Battery | 199 MW | 2021 | 2025 |
| Pinyon Creek Solar LLC projectsusp. C1-54 | Solar + Battery | 199 MW | 2021 | 2024 |
| Queue C2-112 C2-112 | Solar + Battery | 199 MW | 2022 | 2025 |
| Queue C2-115 C2-115 | Solar + Battery | 199 MW | 2022 | 2026 |
| Queue C2-131 C2-131 | Solar + Battery | 199 MW | 2022 | 2026 |
| Queue C2-56 C2-56 | Solar + Battery | 199 MW | 2022 | 2026 |
| Queue C2-57 C2-57 | Solar + Battery | 199 MW | 2022 | 2026 |
| Queue C2-58 C2-58 | Solar + Battery | 199 MW | 2022 | 2026 |
| Queue C2-59 C2-59 | Solar + Battery | 199 MW | 2022 | 2026 |
| Queue C3-132 C3-132 | Solar + Battery | 199 MW | 2023 | 2027 |
| Queue PIS105 PIS105 | Solar + Battery | 199 MW | 2025 | 2026 |
| Queue T2-060 T2-060 | Solar + Battery | 199 MW | 2025 | 2027 |
| Queue T2-062 T2-062 | Solar + Battery | 199 MW | 2025 | 2027 |
| Queue T2-063 T2-063 | Solar + Battery | 199 MW | 2025 | 2027 |
| Queue T2-071 T2-071 | Solar + Battery | 199 MW | 2025 | 2028 |
| Queue T2-055 T2-055 | Solar + Battery | 175 MW | 2025 | 2029 |
| Queue C2-99 C2-99 | Solar + Battery | 166 MW | 2022 | 2026 |
| Queue T2-037 T2-037 | Solar + Battery | 150 MW | 2025 | 2028 |
| Muddy Creek Energy, LLC projectsusp. C1-14 | Solar + Battery | 120 MW | 2021 | 2029 |
| Queue T2-054 T2-054 | Solar + Battery | 100 MW | 2025 | 2027 |
| Steel Solar, LLC project 754 | Solar + Battery | 80 MW | 2016 | 2023 |
| RC Solar Energy LLC project 792 | Solar + Battery | 80 MW | 2016 | 2025 |
| Queue C3-125 C3-125 | Solar + Battery | 75 MW | 2023 | 2027 |
| Queue PIS106 PIS106 | Solar + Battery | 75 MW | 2025 | 2027 |
| Steel Solar, LLC projectsusp. 799 | Solar + Battery | 67 MW | 2016 | 2023 |
| Parowan Solar, LLC project 642 | Solar + Battery | 58 MW | 2015 | 2024 |
| Rocket Solar, LLC projectsusp. 862 | Solar + Battery | 45 MW | 2017 | 2019 |
| Emery Bull Creek Energy, LLC projectsusp. C1-10 | Solar + Battery | 45 MW | 2021 | 2029 |
| PacifiCorp project T2-006 | Solar + Battery | 20 MW | 2025 | 2028 |
| Queue T2-039 T2-039 | Solar + Battery | 20 MW | 2025 | 2026 |
| Queue T2-042 T2-042 | Solar + Battery | 20 MW | 2025 | 2027 |
| Queue T2-043 T2-043 | Solar + Battery | 20 MW | 2025 | 2027 |
| Queue T2-044 T2-044 | Solar + Battery | 20 MW | 2025 | 2027 |
| Queue T2-045 T2-045 | Solar + Battery | 20 MW | 2025 | 2027 |
| Queue T2-046 T2-046 | Solar + Battery | 20 MW | 2025 | 2027 |
| Queue T2-047 T2-047 | Solar + Battery | 20 MW | 2025 | 2027 |
| Queue T2-048 T2-048 | Solar + Battery | 20 MW | 2025 | 2027 |
Browse Utah's full interconnection queue. Compare with operating capacity: 52 operating solar plants in Utah. Nationwide: Solar plants nationwide, Storage plants nationwide.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).