Virginia · Solar
Proposed solar projects in Virginia
There are 111 proposed solar projects in Virginia's interconnection queue, totaling 10.97 GW of requested capacity. The largest is Blackwater Solar at 800 MW, and the median planned online year is 2026.
111
Proposed projects
10.97 GW
Requested capacity
98.8 MW
Average project size
2026
Median planned online year
All proposed solar projects in Virginia
| Type | ||||
|---|---|---|---|---|
| Blackwater Solar AE1-173 | Solar | 800 MW | 2018 | 2030 |
| Randolph Solar AF2-042 | Solar | 500 MW | 2019 | 2032 |
| Zeus Energy, LLC project AG2-570 | Solar | 400 MW | 2025 | 2024 |
| Monarch Solar, LLC project AG2-436 | Solar | 350 MW | 2025 | 2023 |
| Honeybee Solar, LLC AH1-528 | Solar | 300.8 MW | 2025 | 2025 |
| Chickahominy Solar 1 and 2 AC1-164 | Solar | 295 MW | 2016 | 2026 |
| Sycamore Cross Solar AC2-141 | Solar | 240 MW | 2017 | 2026 |
| Axton Solarsusp. AE2-140 | Solar | 201.1 MW | 2019 | 2025 |
| Virginia Electric and Power Company project AG2-077 | Solar | 200 MW | 2025 | 2024 |
| ACE Development Company, LLC project AG2-182 | Solar | 200 MW | 2025 | 2022 |
| Waller Solar I AG1-038 | Solar | 176 MW | 2020 | 2027 |
| Courthouse Solar AF2-222 | Solar | 167 MW | 2020 | 2031 |
| Virginia Electric and Power Company project AG2-069 | Solar | 150 MW | 2025 | 2025 |
| Bellflower Holdings, LLC project AG2-581 | Solar | 150 MW | 2025 | 2024 |
| Big Pine Solar AE2-051 | Solar | 150 MW | 2019 | 2031 |
| Blue Ridge Solar AE1-250 | Solar | 150 MW | 2018 | 2028 |
| Firefly Solar AD2-023 | Solar | 150 MW | 2017 | 2027 |
| Pulaski Solar AF2-106 | Solar | 150 MW | 2020 | 2028 |
| Wild Indigo Solarsusp. AD1-151 | Solar | 150 MW | 2017 | 2026 |
| Riverstone Solar AE1-108 | Solar | 149.5 MW | 2018 | 2027 |
| Enclave Solar Energy Centersusp. AE2-033 | Solar | 149 MW | 2019 | 2027 |
| Maroon Solarsusp. AE1-153 | Solar | 149 MW | 2018 | 2027 |
| Taro Solar LLC project AG2-442 | Solar | 140 MW | 2025 | 2024 |
| Woodridge Solar AE2-092 | Solar | 138 MW | 2019 | 2027 |
| Gibson Solar I AF2-091 | Solar | 134 MW | 2020 | 2029 |
| Virginia Electric and Power Company project AG2-152 | Solar | 131 MW | 2025 | 2024 |
| Waller Solar I AF1-042 | Solar | 131 MW | 2019 | 2027 |
| Red Brick Solar AD2-033 | Solar | 130 MW | 2017 | 2026 |
| Quarter Horse Solar AG1-285 | Solar | 125 MW | 2020 | 2031 |
| Southern Virginia Solar AF1-049 | Solar | 125 MW | 2019 | 2027 |
| CC Solar I AE1-157 | Solar | 120 MW | 2018 | 2028 |
| Chester Solarsusp. AE2-027 | Solar | 120 MW | 2018 | 2027 |
| Boston Hill Solar, LLC project AG2-583 | Solar | 115 MW | 2025 | 2026 |
| Virginia Electric and Power Company project AG2-441 | Solar | 113 MW | 2025 | 2024 |
| Hillandale Solar AE2-291 | Solar | 102 MW | 2019 | 2030 |
| Virginia Electric and Power Company project AG2-068 | Solar | 100 MW | 2025 | 2025 |
| Cumberland Solar, LLC project AG2-151 | Solar | 100 MW | 2025 | 2024 |
| Bakers Pond Solarsusp. AE1-149 | Solar | 100 MW | 2018 | 2026 |
| Blue Rock Solar AE2-259 | Solar | 100 MW | 2019 | 2026 |
| Gibson Solar I AF1-114 | Solar | 100 MW | 2019 | 2028 |
| Cartersville Solar AC2-165 | Solar | 99.9 MW | 2017 | 2027 |
| Firefly Solar AD2-022 | Solar | 96 MW | 2017 | 2027 |
| Knoxville Solar AF1-017 | Solar | 91 MW | 2019 | 2027 |
| Clover Creek Solar AG1-105 | Solar | 90 MW | 2020 | 2030 |
| Dulles Solar and BESS AF1-147 | Solar | 90 MW | 2019 | 2026 |
| Rocky Ford Solar Energy Centersusp. AE2-166 | Solar | 90 MW | 2019 | 2026 |
| Walnut Solar I AD2-039 | Solar | 90 MW | 2018 | 2026 |
| Wild Rose Solar Project AG1-124 | Solar | 90 MW | 2020 | 2024 |
| Virginia Electric and Power Company project AG2-369 | Solar | 86 MW | 2025 | 2025 |
| Waller Solar I AD2-074 | Solar | 86 MW | 2018 | 2027 |
| ACE Development Company, LLC AH1-439 | Solar | 85 MW | 2025 | 2026 |
| Windsor PVI AC2-079 | Solar | 85 MW | 2017 | 2027 |
| Gabriel Energy LLC project AG2-198 | Solar | 80 MW | 2025 | 2024 |
| Virginia Electric and Power Company project AG2-213 | Solar | 80 MW | 2025 | 2025 |
| Horizon Solar West, LLC project AG2-659 | Solar | 80 MW | 2025 | 2025 |
| Cricket Solar AC1-121 | Solar | 80 MW | 2016 | 2029 |
| Seven Bridges Solarsusp. AD1-088 | Solar | 80 MW | 2017 | 2026 |
| Springfield Solar AC1-191 | Solar | 80 MW | 2016 | 2027 |
| Virginia Electric and Power Company project AG2-440 | Solar | 75 MW | 2025 | 2024 |
| Buchanan County Solar AF2-382 | Solar | 75 MW | 2020 | 2029 |
| Sweet Sue Solar AD1-105 | Solar | 74 MW | 2017 | 2026 |
| Knoxville Solar AE2-247 | Solar | 71 MW | 2019 | 2027 |
| Hermes Solar LLC project AH1-133 | Solar | 70 MW | 2025 | 2024 |
| Aries Solar Project LLC project AH1-144 | Solar | 70 MW | 2025 | 2024 |
| Walnut Solar I AC2-110 | Solar | 70 MW | 2017 | 2026 |
| CEP Solar, LLC AH1-343 | Solar | 69 MW | 2025 | 2025 |
| Mountain Pine Arvonia LLC project AH1-546 | Solar | 65 MW | 2025 | 2025 |
| Cerulean Solar and Mulberry BESS AF2-120 | Solar | 62 MW | 2020 | 2031 |
| Couch Creek Solar LLC project AG2-171 | Solar | 60 MW | 2025 | 2024 |
| Cricket Solar AC1-120 | Solar | 60 MW | 2016 | 2029 |
| Moon Corner Solar AG1-135 | Solar | 60 MW | 2020 | 2031 |
| Pigeon Run Solar and Storage AE2-185 | Solar | 60 MW | 2019 | 2031 |
| Gladys Solar AE2-283 | Solar | 53 MW | 2019 | 2031 |
| Virginia Electric and Power Company project AH1-227 | Solar | 51.3 MW | 2025 | 2025 |
| Knoxville Solar AD2-085 | Solar | 51 MW | 2018 | 2027 |
| Beckett Solar AG1-415 | Solar | 50 MW | 2020 | 2028 |
| Henry County Solar Facility AE2-047 | Solar | 50 MW | 2019 | 2028 |
| Sunridge Solar AE2-029 | Solar | 50 MW | 2018 | 2026 |
| Walnut Solar I AC1-065 | Solar | 50 MW | 2016 | 2026 |
| Amelia Energy Facility AF1-294 | Solar | 41 MW | 2019 | 2022 |
| Ho-Fel Solarsusp. AE1-103 | Solar | 40 MW | 2018 | 2026 |
| Staunton Solar AG1-342 | Solar | 36 MW | 2020 | 2030 |
| Redbud-Gaylord 34.5 kVsusp. AG1-045 | Solar | 30 MW | 2020 | 2026 |
| 360 Solar Center, LLC AH1-106 | Solar | 26 MW | 2025 | 2023 |
| 360 Solar Center, LLC AH1-107 | Solar | 26 MW | 2025 | 2023 |
| Amelia Energy Facility AF2-115 | Solar | 25 MW | 2020 | 2022 |
| Virginia Electric and Power Company project AG2-193 | Solar | 20 MW | 2025 | 2023 |
| Virginia Electric and Power Company project AH1-071 | Solar | 20 MW | 2025 | 2023 |
| Bold Camp CF Solar, LLC project AH1-072 | Solar | 20 MW | 2025 | 2024 |
| Bold Camp CF Solar, LLC project AH1-073 | Solar | 20 MW | 2025 | 2024 |
| Virginia Electric and Power Company project AH1-138 | Solar | 20 MW | 2025 | 2022 |
| Amelia Energy Facility, LLC project AH1-280 | Solar | 20 MW | 2025 | 2023 |
| Amelia Energy Facility AG1-021 | Solar | 20 MW | 2020 | 2023 |
| Chester Solar Technology Park AF1-291 | Solar | 20 MW | 2019 | 2027 |
| Harrowgate 1 AE2-212 | Solar | 20 MW | 2019 | 2027 |
| Horsepen Creek Solar I AH1-170 | Solar | 20 MW | 2025 | 2024 |
| Walnut Solar I AE1-004 | Solar | 20 MW | 2018 | 2026 |
| Walnut Solar I AE2-005 | Solar | 20 MW | 2018 | 2026 |
| Winterpock I AE1-074 | Solar | 20 MW | 2018 | 2026 |
| Walnut Solar I AF1-014 | Solar | 19.9 MW | 2019 | 2026 |
Showing the 100 largest of 111 projects by requested capacity.
Browse Virginia's full interconnection queue. Compare with operating capacity: 123 operating solar plants in Virginia. Nationwide: Solar plants nationwide.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition). Data: LBNL backbone through December 31, 2025; ISO-region statuses refreshed monthly (last: July 2026); non-ISO West and Southeast as of the LBNL edition.