State queue · Washington

Washington interconnection queue

207 proposed generation and storage projects — 182 active and 25 suspended — are in Washington's interconnection queue, primarily in the Non-ISO West, totaling 43.33 GW of requested capacity. Solar + Battery leads with 17.20 GW.

207
Proposed projects
43.33 GW
Requested capacity
Solar + Battery
Largest resource type
2027
Median planned online year

Requested capacity by resource type

Solar + Battery 39.7%Battery 20.4%Wind 18.4%Solar 11.7%Gas 4.8%Nuclear 3.2%Hydro 1.3%Other 0.6%

Proposed projects by resource type

Also in the queue (too few for a dedicated page): Nuclear (2), Hydro (2), Other (5).

All proposed projects in Washington

TypeRegion
Queue G0822
G0822
Solar + BatteryWestBenton2.00 GW20222026
Queue G0608
G0608
BatteryWestKlickitat1.20 GW20182027
Queue G0998
G0998
NuclearWestBenton1.12 GW20232030
Queue G0914
G0914
BatteryWestDouglas1.00 GW20232028
Queue G0953
G0953
WindWestLincoln600 MW20232026
Queue G1025
G1025
Solar + BatteryWestDouglas508.5 MW20232029
Queue G0558
G0558
WindWestBenton500 MW20172019
Queue G0656
G0656
BatteryWestGrant500 MW20202023
Queue G0915
G0915
BatteryWestDouglas500 MW20232028
Queue G0916
G0916
BatteryWestDouglas500 MW20232028
Queue G1015
G1015
SolarWestBenton500 MW20232029
Queue G1032
G1032
SolarWestGrant500 MW20232028
Queue G0670
G0670
Solar + BatteryWestBenton500 MW20212025
Queue G0688
G0688
Solar + BatteryWestBenton500 MW20212025
Queue G0920
G0920
Solar + BatteryWestBenton500 MW20232027
Queue G1087
G1087
Solar + BatteryWestYakima500 MW20252031
Queue G0684
G0684
Solar + BatteryWestBenton470 MW20212024
Queue G1016
G1016
SolarWestKlickitat400 MW20232029
Queue G1035
G1035
SolarWestDouglas400 MW20232028
Queue G0668
G0668
Solar + BatteryWestGrant400 MW20212025
Queue G0760
G0760
GasWestGrant400 MW20222025
Queue G0932
G0932
Solar + BatteryWestBenton400 MW20232029
Queue G0933
G0933
Solar + BatteryWestBenton400 MW20232029
Queue G1037
G1037
Solar + BatteryWestBenton400 MW20232030
Queue G1038
G1038
Solar + BatteryWestBenton400 MW20232030
Queue G1039
G1039
Solar + BatteryWestBenton400 MW20232030
Queue G1040
G1040
Solar + BatteryWestBenton400 MW20232030
Queue G1080
G1080
Solar + BatteryWestYakima400 MW20252032
Queue G1081
G1081
Solar + BatteryWestYakima400 MW20252032
Queue G1082
G1082
Solar + BatteryWestYakima400 MW20252032
Queue G1083
G1083
Solar + BatteryWestYakima400 MW20252032
Queue G0589
G0589
SolarWestKlickitat381 MW20182023
Queue CS25-09
CS25-09
Solar + BatteryWestAdams375 MW20252030
Queue TCS-14
TCS-14
WindWestGarfield375 MW20212027
Queue 12-051susp.
12-051
GasWestCowlitz375 MW20122016
Queue G0921
G0921
WindWestThurston357 MW20232030
Queue G0954
G0954
WindWestLincoln350 MW20232026
Queue G0955
G0955
WindWestLincoln350 MW20232026
Queue G0490
G0490
HydroWestDouglas345 MW20132022
Queue G0585
G0585
WindWestKlickitat313 MW20182021
Queue CS24-15
CS24-15
WindWestLincoln300 MW20242029
Queue CS25-11
CS25-11
WindWestGarfield300 MW20252029
Queue G0872
G0872
WindWestGarfield300 MW20232028
Queue G0973
G0973
WindWestMason300 MW20232029
Queue 10
10
Solar + BatteryWestGrant300 MW2023
Queue 9
9
Solar + BatteryWestGrant300 MW2023
Queue 141
141
Solar + BatteryWestThurston300 MW20242030
Queue G0840
G0840
Solar + BatteryWestDouglas300 MW20232027
Queue G0853
G0853
Solar + BatteryWestDouglas300 MW20232027
Queue G1007
G1007
WindWestLewis300 MW20232030
Queue G0761
G0761
WindWestGrant290 MW20222026
Queue G1008
G1008
GasWestClark286 MW20232024
Queue G0844
G0844
Solar + BatteryWestKlickitat280 MW20232026
Queue G0919
G0919
NuclearWestBenton270 MW20232031
Queue CS25-08
CS25-08
BatteryWestSpokane250 MW20252029
Queue G0294
G0294
WindWestColumbia250 MW20072011
Queue G0295
G0295
WindWestColumbia250 MW20072011
Queue G0559
G0559
WindWestBenton250 MW20172019
Queue G1014
G1014
BatteryWestKing250 MW20232029
Queue G1031
G1031
SolarWestKlickitat250 MW20232028
Queue 99susp.
99
BatteryWestKing250 MW20212028
Queue G0683
G0683
WindWestBenton233 MW20212026
Queue G0935
G0935
SolarWestWalla Walla225 MW20232027
Queue CS23-06
CS23-06
WindWestWhitman220.5 MW20232028
Queue 113susp.
113
GasWestLewis218.8 MW20212029
Queue 114susp.
114
GasWestKitsap215 MW20212029
Queue G0753
G0753
Solar + BatteryWestDouglas215 MW20222025
Queue G0817
G0817
Solar + BatteryWestYakima215 MW20222025
Queue G0535
G0535
HydroWestWalla Walla210 MW20162031
Queue S0027
S0027
BatteryWestWalla Walla210 MW20242026
Queue 99
99
Solar + BatteryWestFranklin200 MW20192021
Queue CS25-15
CS25-15
WindWestSpokane200 MW20252030
Queue CS25-17
CS25-17
WindWestSpokane200 MW20252030
Queue G0645
G0645
SolarWestKlickitat200 MW20202026
Queue G0671
G0671
WindWestWalla Walla200 MW20212025
Queue G0819
G0819
WindWestDouglas200 MW20222027
Queue 7
7
SolarWestGrant200 MW2020
Queue 8
8
SolarWestGrant200 MW2022
Queue 1 Pre Jan 2004
1 Pre Jan 2004
WindWestKittitas200 MW20032004
Queue 100susp.
100
BatteryWestPierce200 MW20212028
Queue 101susp.
101
BatteryWestKing200 MW20212028
Queue 103susp.
103
BatteryWestSkagit200 MW20212028
Queue 109susp.
109
BatteryWestKitsap200 MW20212029
Queue 149
149
BatteryWestWhatcom200 MW20242027
Queue 60
60
BatteryWestPierce200 MW20182028
Queue 87
87
BatteryWestSkagit200 MW20202028
Queue 98
98
BatteryWestPierce200 MW20212026
Queue G0639
G0639
Solar + BatteryWestDouglas200 MW20202023
Queue G0660
G0660
Solar + BatteryWestGrant200 MW20202024
Queue G0732
G0732
Solar + BatteryWestBenton200 MW20222027
Queue G0744
G0744
Solar + BatteryWestGrant200 MW20222026
Queue G0820
G0820
Solar + BatteryWestDouglas200 MW20222027
Queue G0979
G0979
Solar + BatteryWestKlickitat200 MW20232029
Queue G1048
G1048
Solar + BatteryWestMason200 MW20232027
Queue CS23-12
CS23-12
BatteryWestFranklin199 MW20232029
Queue CS25-07
CS25-07
WindWestWhitman199 MW20252029
Badger Gap PV I, LLC projectsusp.
C1-37
Solar + BatteryWestKittitas199 MW20212024
Queue T2-027
T2-027
WindWestCowlitz199 MW20252027
Queue 54susp.
54
GasWestGrays Harbor198.8 MW20172026
Queue G0637
G0637
BatteryWestKlickitat190 MW20202022

Showing the 100 largest of 207 projects by requested capacity.

See 142 operating plants in Washington · Region: Non-ISO West.

Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).