Washington · Battery
Proposed battery projects in Washington
There are 48 proposed battery projects in Washington's interconnection queue, totaling 8.86 GW of requested capacity. The largest is Queue G0608 at 1.20 GW, and the median planned online year is 2027.
48
Proposed projects
8.86 GW
Requested capacity
184.5 MW
Average project size
2027
Median planned online year
All proposed battery projects in Washington
| Type | ||||
|---|---|---|---|---|
| Queue G0608 G0608 | Battery | 1.20 GW | 2018 | 2027 |
| Queue G0914 G0914 | Battery | 1.00 GW | 2023 | 2028 |
| Queue G0656 G0656 | Battery | 500 MW | 2020 | 2023 |
| Queue G0915 G0915 | Battery | 500 MW | 2023 | 2028 |
| Queue G0916 G0916 | Battery | 500 MW | 2023 | 2028 |
| Queue CS25-08 CS25-08 | Battery | 250 MW | 2025 | 2029 |
| Queue G1014 G1014 | Battery | 250 MW | 2023 | 2029 |
| Queue 99susp. 99 | Battery | 250 MW | 2021 | 2028 |
| Queue S0027 S0027 | Battery | 210 MW | 2024 | 2026 |
| Queue 100susp. 100 | Battery | 200 MW | 2021 | 2028 |
| Queue 101susp. 101 | Battery | 200 MW | 2021 | 2028 |
| Queue 103susp. 103 | Battery | 200 MW | 2021 | 2028 |
| Queue 109susp. 109 | Battery | 200 MW | 2021 | 2029 |
| Queue 149 149 | Battery | 200 MW | 2024 | 2027 |
| Queue 60 60 | Battery | 200 MW | 2018 | 2028 |
| Queue 87 87 | Battery | 200 MW | 2020 | 2028 |
| Queue 98 98 | Battery | 200 MW | 2021 | 2026 |
| Queue CS23-12 CS23-12 | Battery | 199 MW | 2023 | 2029 |
| Queue G0637 G0637 | Battery | 190 MW | 2020 | 2022 |
| Queue 129 129 | Battery | 170 MW | 2021 | 2029 |
| Queue 102susp. 102 | Battery | 150 MW | 2021 | 2028 |
| Queue G0858 G0858 | Battery | 130 MW | 2023 | 2026 |
| Queue 139 139 | Battery | 130 MW | 2023 | 2028 |
| Queue 112 112 | Battery | 127 MW | 2021 | 2029 |
| Queue 121susp. 121 | Battery | 125 MW | 2021 | 2030 |
| Queue CS25-03 CS25-03 | Battery | 100 MW | 2025 | 2030 |
| Queue G0828 G0828 | Battery | 100 MW | 2022 | 2026 |
| Queue G0922 G0922 | Battery | 100 MW | 2023 | 2026 |
| Queue C2-204 C2-204 | Battery | 100 MW | 2022 | 2024 |
| Queue 145 145 | Battery | 100 MW | 2024 | 2027 |
| Queue 146 146 | Battery | 100 MW | 2024 | 2027 |
| Queue 148 148 | Battery | 100 MW | 2024 | 2028 |
| Queue 150 150 | Battery | 100 MW | 2024 | 2027 |
| Queue 81susp. 81 | Battery | 100 MW | 2020 | 2028 |
| Queue 86 86 | Battery | 100 MW | 2020 | 2030 |
| Queue 124susp. 124 | Battery | 85 MW | 2021 | 2029 |
| Queue G0717 G0717 | Battery | 75 MW | 2021 | 2024 |
| Queue G1076 G1076 | Battery | 46.5 MW | 2025 | 2027 |
| Queue G0733 G0733 | Battery | 30 MW | 2022 | 2025 |
| Queue G0832 G0832 | Battery | 25 MW | 2022 | 2025 |
| Queue G0734 G0734 | Battery | 20 MW | 2022 | 2024 |
| Queue G0829 G0829 | Battery | 20 MW | 2022 | 2026 |
| Queue G0830 G0830 | Battery | 20 MW | 2022 | 2026 |
| Queue G0942 G0942 | Battery | 20 MW | 2023 | 2026 |
| Queue G1058 G1058 | Battery | 20 MW | 2023 | 2027 |
| Queue G1079 G1079 | Battery | 10 MW | 2025 | 2027 |
| Queue 70 70 | Battery | 2.5 MW | 2018 | 2019 |
| Queue CS24-02 CS24-02 | Battery | 0.5 MW | 2024 | 2025 |
Browse Washington's full interconnection queue. Compare with operating capacity: 3 operating storage plants in Washington. Nationwide: Storage plants nationwide.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).