Owner profile
Bullrock-NxtGenREA
Bullrock-NxtGenREA owns or operates 10 generating facilities commissioned between 2024 and 2024, with a combined nameplate capacity of 32.6 MW. The largest share of capacity is solar (100%), located in New York.
Ownership reflects the utility or operator reported to EIA (Form EIA-860); equity ownership of individual facilities may differ.
10
Plants
32.6 MW
Total capacity
1
States
5 MW
Largest: Day Hollow
Capacity mix
Solar 100.0%
Operating plants
| Plant | Fuel | Capacity |
|---|---|---|
| Day Hollow | Solar | 5 MW |
| Jericho | Solar | 5 MW |
| State HWY 17C | Solar | 5 MW |
| Kirkland | Solar | 4.2 MW |
| Arcadia | Solar | 3 MW |
| Hanover Road | Solar | 2.7 MW |
| Angell Road | Solar | 2.2 MW |
| Harris | Solar | 2 MW |
Under construction (2)
| Plant | Fuel | Capacity |
|---|---|---|
| Route 5 & 20 Community Solar Farmconstr. | Solar | 2.3 MW |
| State Route 64N Community Solar Farmconstr. | Solar | 1.2 MW |