Colonial Trail West

A 142.4 MW solar power plant in Surry, Virginia, owned by Dominion Energy Inc., commissioned in 2019.

Facility nameplate · EIA Plant ID 61985Solar
Nameplate capacity
142.4 MW
Primary fuel
Solar
Commissioned
2019
Time in queue (20162019)
3.5 yrs
Owner
Dominion Energy Inc.
Location
Surry, Virginia
Generation (2024)
281.8 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1

This facility was matched to a PJM Interconnection interconnection request (LBNL Queued Up): queued 2016, commercial operation 2019 3.5 years in the queue. See the PJM queue or typical durations.

Reported annual generation

YearGWh
20196.5
2020301.4
2021271.2
2022275
2023260.2
2024281.8

Nearby power plants

PlantFuelCapacityDistance
Spring Grove ISolar97.9 MW~4 km
SurryNuclear1.70 GW~18 km
Gravel NeckNatural Gas407.7 MW~19 km
Cavalier SolarSolar155.6 MW~20 km
Cavalier Solar A2Solar84.4 MW~20 km
Fort Powhatan SolarSolar150 MW~21 km

See all solar plants in Virginia or browse all plants in Virginia.